Site start · Co. Clare
Ennis, Clare
Granted 25 Sep 2024 (final grant issued 31 Oct 2024)
Key facts
- Site start record 2460086 at Ennis, Co. Clare: 48 homes.
- The planning authority is Clare County Council.
- Status: Granted 25 Sep 2024 (final grant issued 31 Oct 2024).
Source: the Clare County Council planning register, as last seen on 12 Jul 2026. Open the council's file
More planning applications in Ennis · Planning applications in Co. Clare
Council register
The council's register shows: Granted on 25 Sep 2024.
Search the Clare planning register
Application details as we last saw them in the national register on 12 Jul 2026.
What and where
48 homes
Commencement Notice for a development comprising 48 no. residential units, (32 no. semi-detached houses, 8 no. terrace houses and 8 no. duplex apartments), ancillary surface car parking, vehicular & pedestrian access to the proposed development including a new road, footpath and cyclepath extensions from the existing development to serve the new units, connection to existing public water supply; foul water drainage services by way of a new foul pumping station including the provision of surface water attenuation outfalling to the west via a headwall and reedbed and all associated site development and landscape works. The planning application is accompanied by an NIS (Natura Impact Statement)
Description as published by the council. Its text starts part-way through a sentence.
- Location
- Ennis, Co. Clare Map
- Council
- Clare County Council
- Planning reference
- 2460086
- Application type
- Commencement Notice
- Owner named on the notice
- Custy Construction Ltd
- Agent named on the notice
- Custy Construction Ltd
Numbers and dates
- Homes
- 48
- Floor area
- 4,979 m²per planning documents
- Project type
- Large residential
- Received
- 29 Feb 2024
- Decision to grant
- 25 Sep 2024
- Final grant
- 31 Oct 2024
- Site start notified
- 25 Dec 2024
Documents and evidence
Check the record
- Council planning fileThe application file 2460086 on eplanning.ie: drawings, reports and the decision.Open the council's file
- From the planning documentsRead from Design statement in the council's file.
- Unit mix
- 4 4-bed semi-detached, 26 3-bed semi-detached, 2 2-bed semi-detached bungalow, 8 2-bed terrace, 4 2-bed ground floor duplex, 4 1-bed first floor duplex
- Floor area
- 4,979 m² (per planning documents)
- Site area
- 1.53 ha
- Applicant in the planning documents
- Finn Properties Limited
- Phasing
- Single phase
- Scope
- Development of 48 residential units with associated car parking, roads, footpaths, cyclepaths, water supply, foul drainage, surface water attenuation, and landscape works.
- Rainwater
- “surface water attenuation outfalling via headwall and reedbed”
- Wastewater
- “foul water drainage services by way of a new foul pumping station”
How we know this
From the Clare County Council planning register, as last seen on 12 Jul 2026. The council's own file is the official record. Facts from the planning documents were read from the documents in that file.
Site starts
Commencement notices for this permission
- 25 Dec 2024Notice filed · phase 1 · Construction of a Duplex Apartments on site 31-32 "Cedar Hill"View the site start
- 25 Dec 2024Notice filed · phase 2 · Construction of a Duplex Apartments on site 39-40 "Cedar Hill"View the site start
- 25 Dec 2024Notice filed · phase 3 · Construction of a Duplex Apartments on site 37-38 "Cedar Hill"View the site start
- 25 Dec 2024Notice filed · phase 4 · Construction of a Duplex Apartments on site 45-46 "Cedar Hill"View the site start
- 31 Dec 2024Notice filed · phase 5 · Development comprising 40 no. residential units...Notice re-filed 3 Jan 2025 for the same works.View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area