Temporary/event · Co. Clare

Smithstown, Shannon, Co. Clare V14VY67

Granted 29 Sep 2025 (final grant issued 7 Nov 2025)

Get updates on this application

We'll email you when building work starts.

We send a confirmation link first. Nothing starts until you click it. You can stop at any time.

Key facts

  • Planning application 2560489 at Smithstown, Shannon, Co. Clare V14VY67: Construction of a new 540 m² fully bunded sodium hypochlorite…
  • The applicant is Chemifloc Ltd. The agent is Pemcas Ltd.
  • It was received by Clare County Council on 6 Aug 2025.
  • Status: Granted 29 Sep 2025 (final grant issued 7 Nov 2025).
  • Work started on site on 23 Mar 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Clare County Council planning register, checked 2 Jun 2026. Open the council's file

Planning applications in Co. Clare

What and where

1) Construction of a new 540 m² fully bunded sodium hypochlorite…

for 1) Construction of a new 540 m² fully bunded sodium hypochlorite building with a 60 m² lower mezzanine floor and 10 m² upper mezzanine floor, including 2No. external underground brine storage tanks; 2) Construction of a new 102 m² mezzanine floor extension to an existing storage area within an existing warehouse; 3) Construction of a new 32 m² extension to an existing ESB substation on site; 4) Demolition of an existing internal ramped accessway and removal of 2 No. existing temporary containers off site; 5) All ancillary site development works and services to facilitate the development including drainage, external plant, external pipework to adjacent storage tank and utility connections. The proposed development site is controlled by an Industrial Emissions Licence (Register No. P0076-02) authorised by the Environmental Protection Agency.

Description as published by the council. Its text starts part-way through a sentence.

Location
Clare V14vy67, Co. Clare Map
Planning reference
2560489
Applicant
Chemifloc Ltd

Numbers and dates

Floor area
744 m²
Project type
Temporary/event
Received
6 Aug 2025
Decision to grant
29 Sep 2025
Final grant
7 Nov 2025
Site start
23 Mar 2026

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start

Outlook

What happens next

Work started on site on 23 Mar 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2560489 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Clare County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.

Site starts

Commencement notices for this permission

  1. 23 Mar 2026Work started · Construction of a new 29.7 m2 extension to an existing ESB substation on site and all...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Clare V14vy67

Get alerts for Co. ClareFree. We email you when new applications appear.

Free email alerts

Get new Clare projects by email

New applications, decisions and site starts in Co. Clare. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

Email alerts for this applicationMore alert options