Planning record · Co. Cork
Ballythomas East, Ballythomas West, Horsehill More Dunderrow Kinsale Co.Cork
Granted 9 Mar 2017 (final grant issued 18 Apr 2017)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 17/4071 at Ballythomas East, Ballythomas West, Horsehill More Dunderrow Kinsale Co.Cork: Planning application.
- It was received by Cork County Council on 17 Jan 2017.
- Status: Granted 9 Mar 2017 (final grant issued 18 Apr 2017).
- Work was due to start on 22 Jun 2017, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 9 Mar 2017.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Planning application
The development will consist of the following works at the existing IE08 production building: (1) Demolition of (a) an existing single-storey section (gross floor space 26.9 m²) of the building, (b) of an existing storage room at first floor level (gross floor space 11.6 m²) and (c) of an existing single-storey drum heating shed (gross floor space 25.9 m²) adjacent to the south of the building (total area for demolition is 64.4 m²); (2) The construction of (a) a new single storey extension of gross floor space 78 m² and height not exceeding 4.9m and (b) a new three storey extension of gross floor space 250.2 m² and total height not exceeding 15.8m, to be constructed in 2 phases (total new floorspace is 328.2 m²); (3) The provision of a new internal lobby (gross floor space 34 m²) including alterations to the existing western elevation to provide a new entrance; (4) All associated internal modifications to facilitate the 2 no. new extensions and the new internal lobby; and (5) All associated site development works.
- Location
- Ballythomas West, Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 17/4071
Numbers and dates
- Floor area
- 250 m²
- Project type
- Planning record
- Received
- 17 Jan 2017
- Decision to grant
- 9 Mar 2017
- Final grant
- 18 Apr 2017
- Site start notified
- 22 Jun 2017
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 17/4071.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 22 Jun 2017Notice filed · Complete a single storey and a three storey extension to IE8 buildingView the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.