Commercial new build · Co. Cork
Ballintaggart and Ballybricken Townlands Ringaskiddy Co Cork
Granted 8 Sep 2017 (final grant issued 10 Nov 2017)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 17/5864 at Ballintaggart and Ballybricken Townlands Ringaskiddy Co Cork: 2 no. storage sheds adjacent to the existing Organic Synthesis Plant…
- It was received by Cork County Council on 19 Jul 2017.
- Status: Granted 8 Sep 2017 (final grant issued 10 Nov 2017).
- Work was due to start on 1 Mar 2018, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 8 Sep 2017.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
2 no. storage sheds adjacent to the existing Organic Synthesis Plant…
Construction of 2 no. storage sheds adjacent to the existing Organic Synthesis Plant 4 Finished Goods Building at their production facility. The proposed development is covered by an existing Industrial Emissions Directive Licence No. P0013-04. The development refers to a modification to an establishment to which the Major Accident directive applies.
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 17/5864
Numbers and dates
- Project type
- Commercial new build
- Received
- 19 Jul 2017
- Decision to grant
- 8 Sep 2017
- Final grant
- 10 Nov 2017
- Site start notified
- 1 Mar 2018
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 17/5864.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 1 Mar 2018Notice filed · phase 1 · OSP4 Building, Pfizer Ireland, Ringaskiddy - Construction of a Single Storey Pallet...View the site start
- 1 Mar 2018Notice filed · phase 2 · OSP4, Pfizer API Plant, Ringaskiddy - Construction of a Single Storey extension to...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.