Commercial new build · Co. Cork
Midleton Distillery Park North Midleton Co. Cork
Granted 26 Mar 2018 (final grant issued 3 May 2018)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 18/4216 at Midleton Distillery Park North Midleton Co. Cork: 2 storey office building with roof top solar panels.
- It was received by Cork County Council on 29 Jan 2018.
- Status: Granted 26 Mar 2018 (final grant issued 3 May 2018).
- Work was due to start on 20 Jun 2018, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 12 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 26 Mar 2018.
Search the Cork planning register
Application details as we last saw them in the national register on 12 Jun 2026.
What and where
2 storey office building with roof top solar panels
Construction of a 2 storey office building with roof top solar panels. The proposed development makes provision for the alteration and extension of the existing car park, the erection of a bicycle shelter and all ancillary fencing, landscaping and site development works. The proposed development is for modifications to an establishment to which the Major Accident Directive applies and is for the purpose of activity requiring an integrated pollution control licence [Industrial Emissions Directive (IED) Licence].
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 18/4216
Numbers and dates
- Project type
- Commercial new build
- Received
- 29 Jan 2018
- Decision to grant
- 26 Mar 2018
- Final grant
- 3 May 2018
- Site start notified
- 20 Jun 2018
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 18/4216.Search the register
How we know this
From the Cork County Council planning register, as last seen on 12 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 20 Jun 2018Notice filed · Construction of a two-storey office building for IDL at Midleton DistilleryView the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.