Commercial new build · Co. Cork
Brinny Innishannon Co. Cork
Granted 9 May 2018 (final grant issued 20 Jun 2018)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 18/4642 at Brinny Innishannon Co. Cork: Extension to the existing Building 21.
- It was received by Cork County Council on 15 Mar 2018.
- Status: Granted 9 May 2018 (final grant issued 20 Jun 2018).
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 9 May 2018.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Extension to the existing Building 21
An extension to the existing Building 21 (Planning Ref. 17/4830) and associated works as follows: The works include the construction of a new 2 storey extension with ground floor mezzanine to the East elevation. The extension will comprise a freezer room, staging areas and the provision of roof mounted plant within the curtilage of a new parapet. The extension has a total floor area of 592 square metres and is 15.7 metres high. The works also include landscaping, underground and overground utilities, yards and associated siteworks. The works also include new external items of plant and equipment. The application consists of an activity for which an Industrial Emissions license under Part IV of the Environmental Protection Agency Act 1992 (as amended) is required.
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 18/4642
Numbers and dates
- Floor area
- 592 m²
- Estimated construction value
- €630k to €790kOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Commercial new build
- Received
- 15 Mar 2018
- Decision to grant
- 9 May 2018
- Final grant
- 20 Jun 2018
- Site start notified
- 6 Jul 2018
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Site history
This site's history
-
Earlier permission 17/4830 for this site: granted 30 May 2017.
The development will consist of a Biopharmaceutical Manufacturing Facility and associated works; • The alterations and extensions to… Named in this application's description
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 18/4642.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 6 Jul 2018Notice filed · Construction of a Two Storey Extension onto the Existing Building No 21 at MSD Brinny...View the site start
- Completion certificate recordedRecorded in Jul 2018 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area