- Planning application 18/5215 at Loreto Convent Lighthouse Road Knockaverry Youghal, Co. Cork: ~32 homes.
- It was received by Cork County Council on 14 May 2018.
- Status: Granted 26 Oct 2018 (final grant issued 3 Dec 2018).
- Work was due to start on 4 Mar 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 26 Oct 2018.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
~32 homes
1) The renovation, change of use and changes to the elevations of 4 no. existing structures (Blocks 1, 2, 4 &5) previously used as school buildings, for use as on the site for use as 32no apartments including the addition of 1 no. additional storey, entrance lobby staircase and elevator to front of Block 1; 2) The renovation, change of use and change of use to the elvations and 1 no. existing structure (Block 3), previously used as convent residence, for use as 6 no. apartments; 3) Partial demolition of Blocks2 and 3; 4) The construction of 3 no. new 2-storey houses; 5) The construction of a new three-storey building for use as 8 no. duplex and 4 no. apartments; 6) The provision of 3 no. residential serviced sites accessed from Golf Links road; 7) Retention for previously renovated structure on the site, previously used as a gate lodge (block 8) for use as a site office, marketing and information suite. The development consists of works to a Protected Structure (RPS.2801 and RPS.2802) as well as works adjacent to protected structure. Permission is also sought for all ancillary site services including hard standing, lighting, parking, landscaping areas, construction of refuse compound, connection to public utilities, and other ancillary site works required to complete the development.
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 18/5215
Numbers and dates
- Homes
- ~32estimated from the application
- Estimated construction value
- €4.7m to €8.7mOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Protected structure
- Received
- 14 May 2018
- Decision to grant
- 26 Oct 2018
- Final grant
- 3 Dec 2018
- Site start notified
- 4 Mar 2024
- Protected structure
- Yes
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 18/5215.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 4 Mar 2024Notice filed · Material Alterations and Material Change of Use of existing school building and the...View the site start