Works to a house · Co. Cork

Gortnalicky Clondrohid Macroom Co. Cork

Granted 18 Jul 2018 (final grant issued 23 Aug 2018)

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email

Key facts

  • Planning application 18/5367 at Gortnalicky Clondrohid Macroom Co. Cork: Combined heat and power plant.
  • It was received by Cork County Council on 25 May 2018.
  • Status: Granted 18 Jul 2018 (final grant issued 23 Aug 2018).
  • Work was due to start on 22 Oct 2018, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register

Planning applications in Co. Cork

Council register

The council's register shows: Granted on 18 Jul 2018.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Combined heat and power plant

Construction of combined heat and power plant consisting of a generator house, electrical room, external boiler and ancillary equipment.

Location
Co. Cork Map
Planning reference
18/5367

Numbers and dates

Project type
Works to a house
Received
25 May 2018
Decision to grant
18 Jul 2018
Final grant
23 Aug 2018
Site start notified
22 Oct 2018

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 22 Oct 2018, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 18/5367.Search the register

How we know this

From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 22 Oct 2018Notice filed · Construction of Combined heat and power plant consisting of a generator house...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Co. Cork

Get alerts for Co. CorkFree. We email you when new applications appear.

Free email alerts

Get new Cork projects by email

New applications, decisions and site starts in Co. Cork. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options