House extension · Co. Cork
18 Laburnum Lawn, Bishopstown, Cork
Granted 21 Nov 2018 (final grant issued 2 Jan 2019)
We no longer update this application, so we can't email you about it. Get new planning applications in Bishopstown by email
Key facts
- Planning application 1838068 at 18 Laburnum Lawn, Bishopstown, Cork: Demolish part extension to rear and construct a two-storey extension…
- It was received by Cork City Council on 28 Sep 2018.
- Status: Granted 21 Nov 2018 (final grant issued 2 Jan 2019).
Source: the Cork City Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Bishopstown · Planning applications in Co. Cork
Council register
The council's register shows: Granted on 21 Nov 2018.
Search the Cork City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Demolish part extension to rear and construct a two-storey extension…
Permission to demolish part extension to rear and construct a two-storey extension to side and rear of dwelling with associated site works.
- Location
- Bishopstown, Co. Cork Map
- Council
- Cork City Council
- Planning reference
- 1838068
Numbers and dates
- Project type
- House extension
- Received
- 28 Sep 2018
- Decision to grant
- 21 Nov 2018
- Final grant
- 2 Jan 2019
- Site start notified
- 13 May 2021
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning fileThe application file 1838068 on planning.corkcity.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Cork City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 13 May 2021Notice filed · Extension 18 Laburnum Lawn - Construction of a two storey extension to side and rear of...View the site start
- Full completion certificate recordedRecorded in May 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers the work listed on the certificate; later phases can have their own. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area