Public / civic · Co. Cork

De La Salle Secondary School Gurteenroe Macroom Co. Cork

Granted 21 Nov 2019 (final grant issued 6 Jan 2020)

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email

Key facts

  • Planning application 19/5760 at De La Salle Secondary School Gurteenroe Macroom Co. Cork: Prefabricated detached school building incorporating classrooms.
  • It was received by Cork County Council on 12 Jul 2019.
  • Status: Granted 21 Nov 2019 (final grant issued 6 Jan 2020).

Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register

Planning applications in Co. Cork

Council register

The council's register shows: Granted on 21 Nov 2019.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Prefabricated detached school building incorporating classrooms

Construction of a prefabricated detached school building incorporating classrooms, toilets and ancillary accommodation together with carparking, ball blocking structure and all ancillary site works.

Location
Co. Cork Map
Planning reference
19/5760

Numbers and dates

Project type
Public / civic
Received
12 Jul 2019
Decision to grant
21 Nov 2019
Final grant
6 Jan 2020
Site start notified
27 Feb 2020

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 19/5760.Search the register

How we know this

From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 27 Feb 2020Notice filed · phase 1 · Civils Works - construction of foundation pad layout for prefabricated building...View the site start
  2. 27 Feb 2020Notice filed · phase 2 · Installation of a prefabricated detached school building incorporating classrooms...View the site start
  3. Completion certificate recordedRecorded in Feb 2020 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  4. Completion certificate recordedRecorded in Feb 2020 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Co. Cork

Get alerts for Co. CorkFree. We email you when new applications appear.

Free email alerts

Get new Cork projects by email

New applications, decisions and site starts in Co. Cork. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options