Public / civic · Co. Cork
Freemount National School Knockaneglass East Freemount Charleville, Co. Cork
Granted 17 Dec 2019 (final grant issued 27 Jan 2020)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 19/6329 at Freemount National School Knockaneglass East Freemount Charleville, Co. Cork: Extension containing a classroom and an assisted shower room.
- It was received by Cork County Council on 25 Sep 2019.
- Status: Granted 17 Dec 2019 (final grant issued 27 Jan 2020).
- Work was due to start on 16 Jun 2023, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 17 Dec 2019.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Extension containing a classroom and an assisted shower room
An extension containing a classroom and an assisted shower room and all associated site works.
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 19/6329
Numbers and dates
- Project type
- Public / civic
- Received
- 25 Sep 2019
- Decision to grant
- 17 Dec 2019
- Final grant
- 27 Jan 2020
- Site start notified
- 16 Jun 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 19/6329.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 16 Jun 2023Notice filed · Construction of a Single Storey extension to the side of the existing school. The...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.