Protected structure · Co. Cork
The Patrician Academy/An Acadamh Paitríoch Fair Street/Sráid an Aonaigh Mallow/Mala Co. Cork/Co. Chorcaí
Granted 6 Aug 2020 (final grant issued 10 Sep 2020)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 19/6345 at The Patrician Academy/An Acadamh Paitríoch Fair Street/Sráid An Aonaigh Mallow/Mala Co. Cork/Co. Chorcaí: Part single-storey, part three-storey extension to the existing…
- It was received by Cork County Council on 26 Sep 2019.
- Status: Granted 6 Aug 2020 (final grant issued 10 Sep 2020).
- Work was due to start on 7 Jun 2022, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 6 Aug 2020.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Part single-storey, part three-storey extension to the existing…
The development will consist of a part single-storey, part three-storey extension (c. 3,307 m²) to the existing school building (Protected Structure) to replace the previous 2-storey extension to the north-east of the application site which was destroyed by fire damage. The proposed extension will connect to the eastern elevation of the Protected Structure at the ground and first floor levels and will accommodate 11 no. classrooms and ancillary teacher and pupil facilities and a 2 no. classroom SNU unit with ancillary teacher and pupil facilities. The development will include the demolition of (i) the existing two-storey link building/entrance lobby (c. 111 m²) connected to the eastern elevation of the Protected Structure; (ii) the existing detached, single-storey building (c. 97 m²) adjacent to the eastern elevation of the Protected Structure; (iii) the existing part single-storey, part 2-storey wood work building (c. 377 m²) adjacent to the south-western site boundary; and (iv) a single storey storage building (c. 72 m²) adjacent to the north-eastern site boundary. The development will also include the removal of 7 no. existing pre-fabricated structures (c. 906 m²) generally located to west of the Protected Structure and within the central/southern portion of the site. The proposed development will also include 1 no. single storage building (c. 90 m²) adjacent to the north-eastern site boundary; the demolition of the existing entrance gate and boundary wall at the eastern site boundary at Fair Street and its replacement with a new set back entrance gate and boundary treatment including school signage; the widening of the existing vehicular entrance to the site at the southern site boundary, including reinstatement works to the existing boundary wall and pillars; 29 no. car parking spaces, including 4 no. universal access parking spaces; school signage; photovoltaic panels at roof level; piped infrastructure and ducting, including the diversion of existing site services; 1 no. attenuation tank; changes in level; site landscaping; revised internal vehicular and pedestrian connections; boundary treatments; bicycle parking; and, all associated site development and excavation works above and below ground. No changes are proposed to the existing gym, science lab and art buildings within the application site on foot of this planning application. The Patrician Academy is a Protected Structure (RPS Reg. No. 78). [Is é a bheaidh san fhorbairt, síneadh aon stór
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 19/6345
Numbers and dates
- Project type
- Protected structure
- Received
- 26 Sep 2019
- Decision to grant
- 6 Aug 2020
- Final grant
- 10 Sep 2020
- Site start notified
- 7 Jun 2022
- Protected structure
- Yes
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 19/6345.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 7 Jun 2022Notice filed · phase 1 · Single storey technology classroom buildingView the site start
- 7 Jun 2022Notice filed · phase 2 · Part single-storey, part three-storey extension to the existing school building...View the site start
- 17 Jun 2022Notice filed · phase 3 · Construction of a Single-storey storage building.View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.