Commercial new build · Co. Cork

Ballintaggart and Ballybricken Townlands Ringaskiddy Co. Cork

Granted 1 Apr 2020 (final grant issued 30 Jun 2020)

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email

Key facts

  • Planning application 20/4230 at Ballintaggart and Ballybricken Townlands Ringaskiddy Co. Cork: 1 no. one storey modular building for office use and 1 no. one storey…
  • It was received by Cork County Council on 11 Feb 2020.
  • Status: Granted 1 Apr 2020 (final grant issued 30 Jun 2020).
  • Work was due to start on 21 Dec 2020, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register

Planning applications in Co. Cork

Council register

The council's register shows: Granted on 1 Apr 2020.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

1 no. one storey modular building for office use and 1 no. one storey…

The erection of 1 no. one storey modular building for office use and 1 no. one storey modular building for welfare use in the existing recycle centre compound, 2 no. one storey modular buildings both for office use to the north and 1 no. one storey modular building for office use to the north west of the existing laboratory building and all associated site works at their production facility. The site currently operates under an Industrial Emissions (IE) licence (P0013-04) under part IV of the Environmental Protection Agency Act 1992 (as amended for the Protection of the Environment Act 2003). The new development is on a site to which the Chemical Act (Control of Major Accident Hazards Involving Dangerous Substances) regulations 2015 (S.I. 209 of 2015) applies.

Location
Co. Cork Map
Planning reference
20/4230

Numbers and dates

Project type
Commercial new build
Received
11 Feb 2020
Decision to grant
1 Apr 2020
Final grant
30 Jun 2020
Site start notified
21 Dec 2020

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 21 Dec 2020, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 20/4230.Search the register

How we know this

From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 21 Dec 2020Notice filed · phase 1 · Construction of a single storey Modular Building (Office 2) to the North of the existing...View the site start
  2. 21 Dec 2020Notice filed · phase 2 · The construction of a single storey Modular Building (Office 1) to the North of the...View the site start
  3. 21 Apr 2022Notice filed · phase 3 · The construction of a single Modular Building (Office) located in the existing Recycling...View the site start
  4. 21 Apr 2022Notice filed · phase 4 · The construction of a single storey Modular Building (Welfare Facility) located in the...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Co. Cork

Get alerts for Co. CorkFree. We email you when new applications appear.

Free email alerts

Get new Cork projects by email

New applications, decisions and site starts in Co. Cork. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options