Commercial new build · Co. Cork
Brinny Innishannon Co. Cork
Granted 27 Jul 2020 (final grant issued 31 Aug 2020)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 20/5110 at Brinny Innishannon Co. Cork: 50 m² single storey extension to building 22.
- It was received by Cork County Council on 3 Jun 2020.
- Status: Granted 27 Jul 2020 (final grant issued 31 Aug 2020).
- Work was due to start on 21 Sep 2020, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 27 Jul 2020.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
50 m² single storey extension to building 22
A 50 m² single storey extension to building 22, which will be used for the purposes of gowning, staging and entry into an existing laboratory, including all associated modifications and site development works. This application relates to a development, which comprises an activity for which an Industrial Emissions License under part IV of the Environment Protection Agency 1992 (as amended) is required.
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 20/5110
Numbers and dates
- Floor area
- 50 m²
- Project type
- Commercial new build
- Received
- 3 Jun 2020
- Decision to grant
- 27 Jul 2020
- Final grant
- 31 Aug 2020
- Site start notified
- 21 Sep 2020
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 20/5110.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 21 Sep 2020Notice filed · MSD Brinny - QO Labs Project - works to the ground and first floors of Building 22...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.