One-off house · Co. Cork
Rodeen Castletownbere Co. Cork
Granted 8 Jan 2021 (final grant issued 10 Feb 2021)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 20/559 at Rodeen Castletownbere Co. Cork: Demolition of existing commercial shed.
- It was received by Cork County Council on 9 Oct 2020.
- Status: Granted 8 Jan 2021 (final grant issued 10 Feb 2021).
- Work was due to start on 10 Mar 2021, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 8 Jan 2021.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Demolition of existing commercial shed
(i) Demolition of existing commercial shed, (ii) Construction of new dwelling house, (iii) installation of wastewater treatment system and (iv) all associated site works
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 20/559
Numbers and dates
- Homes
- ~1estimated from the application
- Project type
- One-off house
- Received
- 9 Oct 2020
- Decision to grant
- 8 Jan 2021
- Final grant
- 10 Feb 2021
- Site start notified
- 10 Mar 2021
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 20/559.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 10 Mar 2021Notice filed · Construction of detached two storey house and all associated site worksView the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.