Demolition · Co. Cork
Dinish Island Castletownbere Co. Cork
Granted 28 Jun 2022 (final grant issued 2 Aug 2022)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email
Key facts
- Planning application 22/187 at Dinish Island Castletownbere Co. Cork: Demolish existing workshop building.
- It was received by Cork County Council on 16 Mar 2022.
- Status: Granted 28 Jun 2022 (final grant issued 2 Aug 2022).
- Work was due to start on 19 Dec 2022, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 28 Jun 2022.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Demolish existing workshop building
(1) Demolish existing workshop building, (2) Construct new workshop building with staff facilities, site boundary fence and vehicular entrances, (3) Install solar PV Panels on roof of proposed workshop building, (4) Construct internal access roadway and footpaths, (5) Construction of new waste storage shed, inclusive of all ancillary site works
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 22/187
Numbers and dates
- Project type
- Demolition
- Received
- 16 Mar 2022
- Decision to grant
- 28 Jun 2022
- Final grant
- 2 Aug 2022
- Site start notified
- 19 Dec 2022
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 22/187.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 19 Dec 2022Notice filed · CTB Harbour Support Facilities - Construction of a steel portal frame workshop building...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.