One-off house · Co. Cork
Hacketstown Kilbrittain Co Cork
Granted 21 Sep 2023
Key facts
- Planning application 23/5355 at Hacketstown Kilbrittain Co Cork: New dwelling house.
- It was received by Cork County Council on 30 Jun 2023.
- Status: Granted 21 Sep 2023.
- Work started on site on 7 Feb 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Since you last looked
Worked out in this browser from the record's own dates. We do not send emails about it.
Council register
The council's register shows: Granted on 21 Sep 2023.
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
New dwelling house
Construct a new dwelling house.
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 23/5355
Numbers and dates
- Homes
- ~1estimated from the application
- Project type
- One-off house
- Received
- 30 Jun 2023
- Granted
- 21 Sep 2023
- Site start
- 7 Feb 2024
Timeline
- Application received
- Granted
- Site start
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 23/5355 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 7 Feb 2024Work started · Opt Out- Construction of a new dwelling house
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.