- Planning application 23/5983 at Tullagreen & Carrigtohill Carrigtwohill Co.Cork: New waste water treatment area.
- It was received by Cork County Council on 3 Oct 2023.
- Status: Granted 15 Apr 2024 (final grant issued 17 May 2024).
- Work was due to start on 28 Jun 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 15 Apr 2024.
Search the Cork planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
New waste water treatment area
The Development will consist of a new waste water treatment area. Works will include the construction of a standalone single storey roofed tankage structure, a two-storey dewatering/sludge building, a concrete slab area, access road, 3 no. vehicle parking bays and associated ground level mounted equipment and storage area. This application is for an amendment to the WWT area previously approved under reference no. 22/4839. The proposed development is on an existing manufacturing site to which the Major Accidents Directive applies, and to which an Industrial Emissions Licence and an Integrated Pollution Control Licence that are regulated by the Environmental Protection Agency (EPA) applies.
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 23/5983
Numbers and dates
- Project type
- Commercial new build
- Received
- 3 Oct 2023
- Decision to grant
- 15 Apr 2024
- Final grant
- 17 May 2024
- Site start notified
- 28 Jun 2024
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Site history
This site's history
-
Earlier permission 22/4839 for this site: granted 6 Oct 2022.
The demolition of existing switch room and an existing drum store and the construction of a new 3 storey manufacturing building to the east… Named in this application's description
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 23/5983.Search the register
How we know this
From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 28 Jun 2024Notice filed · Merck WWTP Upgrade Project - Construction of a Two Storey Sludge Dewatering Building to...View the site start