Key facts

  • Planning application 23/6109 at Knocknamadderee Cloyne Co. Cork: Change of plan to the planning application granted under planning…
  • It was received by Cork County Council on 18 Oct 2023.
  • Status: Granted 8 Dec 2023 (final grant issued 2 Feb 2024).
  • Work was due to start on 30 Oct 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Cork County Council planning register, as last seen on 2 Jun 2026. Search the council's register

Planning applications in Co. Cork

Council register

The council's register shows: Granted on 8 Dec 2023.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Change of plan to the planning application granted under planning…

Permission for 1) a Change of plan to the planning application granted under planning Reference 186022; 2) The construction of new single storey detached dwelling with first floor mezzanine; 3) A new wastewater treatment unit and percolation area; and including all associated site works.

Location
Co. Cork Map
Planning reference
23/6109

Numbers and dates

Homes
~1estimated from the application
Project type
One-off house
Received
18 Oct 2023
Decision to grant
8 Dec 2023
Final grant
2 Feb 2024
Site start notified
30 Oct 2024

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Site history

This site's history

  1. Earlier permission 18/6022 for this site: granted 12 Feb 2019.

    To construct a dwelling house, partially single storey and partially 2 storey, together with a shed/workshop for use incidental to the… Named in this application's description

Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.

Outlook

What happens next

Work was due to start on 30 Oct 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 23/6109.Search the register

How we know this

From the Cork County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 30 Oct 2024Notice filed · Construction of single storey detached dwellingView the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Co. Cork

Get alerts for Co. CorkFree. We email you when new applications appear.

Free email alerts

Get new Cork projects by email

New applications, decisions and site starts in Co. Cork. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options