Site start · Co. Cork
Tower, Cork
Site start 17 Oct 2024
Archived record
This application has left our current planning lists, so this page is no longer updated. We last saw it in the council's register on 12 Jul 2026. The details below are as they were then. The council's register has the current status.
Search the Cork City planning registerCurrent planning applications in Tower
What and where
(A) The demolition of an existing cottage and for the construction of…
Permission for (A) The demolition of an existing cottage and for the construction of a new dormer style dwelling with connection to mains sewer and all associated site development works. (B) Permission for retention is also sought for widening of existing vehicular entrance and front boundary wall as constructed.
- Location
- Tower, Co. Cork Map
- Council
- Cork City Council
- Planning reference
- 2342258
Key facts
- Project type
- Demolition
- Site start
- 17 Oct 2024
Documents and evidence
Check the record
- Council planning fileThe application file 2342258 on planning.corkcity.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Cork City Council planning register, as last seen on 12 Jul 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 17 Oct 2024Work started · The demolition of an existing cottage and for the construction of a new dormer style...
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.