Rathealy Road Rath-Healy Rathealy Fermoy Co Cork

Granted 10 Oct 2024 (final grant issued 15 Nov 2024)

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Cork by email

Key facts

  • Planning application 24/5553 at Rathealy Road Rath-Healy Rathealy Fermoy Co Cork: Extension to the existing manufacturing facility.
  • It was received by Cork County Council on 16 Aug 2024.
  • Status: Granted 10 Oct 2024 (final grant issued 15 Nov 2024).
  • Work was due to start on 9 Jan 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Cork County Council planning register, as last seen on 26 Jun 2026. Search the council's register

Planning applications in Co. Cork

Council register

The council's register shows: Granted on 10 Oct 2024.

Application details as we last saw them in the national register on 26 Jun 2026.

What and where

Extension to the existing manufacturing facility

Permission for an extension to the existing manufacturing facility. The development shall consist construction of the following, 1) A new two-storey extension to the existing production space incorporating a mezzanine floor and office space, 2) A new single-storey patio extension to the canteen, 3) A new concrete yard extension (1,090 m²), 4) The provision of a new dedicated HGV entrance onto Rathealy Road, 5) An extension of the existing public footpath on Rathealy Road, 6) landscaping, and all associated works. The Natura Impact Statement will be submitted to the Planning Authority with the application.

Location
Co. Cork Map
Planning reference
24/5553

Numbers and dates

Floor area
1,090 m²
Project type
Commercial new build
Received
16 Aug 2024
Decision to grant
10 Oct 2024
Final grant
15 Nov 2024
Site start notified
9 Jan 2025

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 9 Jan 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

Work packages named so far

  • Roads and site development worksNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 24/5553.Search the register

How we know this

From the Cork County Council planning register, as last seen on 26 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 9 Jan 2025Notice filed · phase 1 · Extension to existing manufacturing facility and associated material alterations.View the site start
  2. 13 Oct 2025Notice filed · phase 2 · Single storey extension to industrial building to provide an ancillary canteen space.View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Co. Cork

Get alerts for Co. CorkFree. We email you when new applications appear.

Free email alerts

Get new Cork projects by email

New applications, decisions and site starts in Co. Cork. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options