Protected structure · Co. Cork
Hibernian Way Mallow Co.Cork
Granted 16 Oct 2025 (final grant issued 21 Nov 2025)
Key facts
- Planning application 25/4200 at Hibernian Way Mallow Co.Cork: ~9 homes.
- It was received by Cork County Council on 13 Feb 2025.
- Status: Granted 16 Oct 2025 (final grant issued 21 Nov 2025).
- Permission was granted on 16 Oct 2025 and the final grant issued on 21 Nov 2025. No site start has been filed yet. The next step is a commencement notice, filed before building work begins; the start date and who will build it are not known yet.
Source: the Cork County Council planning register, checked 2 Jun 2026. Open the council's file
Since you last looked
Worked out in this browser from the record's own dates.
What and where
~9 homes
Permission for the demolition of existing commercial units and 1 no. residential unit, part of a block wall and stone wall and the construction of 9 no. residential units in total consisting of 7 no. town houses, 2 no. apartments, hard landscaping, planters, communal storage area and associated site works. The proposed development is within the Mallow ACA.
- Location
- Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 25/4200
Numbers and dates
- Homes
- ~9estimated from the application
- Estimated construction value
- €1.3m to €2.5mOur estimate from stated homes and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Protected structure
- Received
- 13 Feb 2025
- Decision to grant
- 16 Oct 2025
- Final grant
- 21 Nov 2025
Timeline
- Application received
- Decision to grant
- Final grant issued
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 25/4200 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Cork County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.
Explore the area