Energy · Co. Cork
Kilshinahan, Timoleague, Co. Cork
Granted 19 Feb 2026 (final grant issued 2 Apr 2026)
Key facts
- Planning application 25/6532 at Kilshinahan, Timoleague, Co. Cork: C.5MW solar farm.
- It was received by Cork County Council on 20 Nov 2025.
- Status: Granted 19 Feb 2026 (final grant issued 2 Apr 2026).
- Permission was granted on 19 Feb 2026 and the final grant issued on 2 Apr 2026. No site start has been filed yet. The next step is a commencement notice, filed before building work begins; the start date and who will build it are not known yet.
Source: the Cork County Council planning register, checked 2 Jun 2026. Search the council's register
More planning applications in Timoleague · Planning applications in Co. Cork
What and where
C.5MW solar farm
A c.5MW solar farm comprising approximately 14,000 photovoltaic panels on ground mounted frames, 1 no. single storey transformer station (15 m²), 1 no. single storey delivery station (53 m²), 2 no. single storey spare parts storage containers (15 m² each), security fencing, CCTV, landscaping and all other ancillary development works. The solar panels will be arranged within a developable area of approximately 8.6 ha at Kilshinahan, Timoleague, Co. Cork. The proposed development will consist of the construction and completion of the solar farm as permitted by and commenced under Planning Permission Ref. 15/6968, extended by Ref. 21/4496 and modified by Ref. 22/6452, with proposed minor changes to that which was permitted to the site layout, as shown in the permitted site layout drawings (Drawing Ref. No.s 4332_2005_A, 4332_2006_A and 4332_2007_A), including array arrangement and internal track route, and minor changes to the fence alignment along the north west boundary; and the addition of a second single storey spare parts storage container (15 m²) (2 no. single storey spare parts storage containers in total). It is anticipated that works under the extant planning permissions will commence with the approved site clearance works, access roads and temporary internal tracks/roads, fencing and gates, and the proposed development will incorporate those works and such further construction and completion of the solar farm as modified by the proposed grant of planning permission the subject of this application. A 2-year permission is sought, with works expected to commence in Q1 2026 under the extant permissions and this permission is sought to secure the completion of the solar farm development. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply.
- Location
- Timoleague, Co. Cork Map
- Council
- Cork County Council
- Planning reference
- 25/6532
Numbers and dates
- Floor area
- 98 m²
- Project type
- Energy
- Received
- 20 Nov 2025
- Decision to grant
- 19 Feb 2026
- Final grant
- 2 Apr 2026
Timeline
- Application received
- Decision to grant
- Final grant issued
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 25/6532.Search the register
How we know this
From the Cork County Council planning register, checked 2 Jun 2026. We link to the council's own file so you can check the official record before you act.
Explore the area