Protected structure, Cork, Cork - Planning Application 2543612
Cork / Cork / Cork, Cork
Source-linked planning record
Protected structure, Cork, Cork - Planning Application 2543612
Cork / Cork / Cork, Cork- PB ref
- PB-27642
- Plan ref
- 2543612
- Authority
- Cork City Council
- Stage / date
- Commencement / 13 Nov 2025
- Est. value band
- Value not disclosed
- Project class
- Protected structure
- Promoter
- Dalata Hotel Group Plc
- Architect / agent
- Summerhill Construction Co Ltd
Source: http://planning.corkcity.ie/AppFileRefDetails/2543612/0
Key facts
Lead summary
- Source
- Owner-supplied commencement export
- Planning authority
- Cork City Council
- Application reference
- 2543612
- Applicant
- Dalata Hotel Group Plc
- Agent
- Summerhill Construction Co Ltd
- Decision stage
- Commencement
- Commenced
- 13 Nov 2025
- Builder / developer
- Summerhill Construction Co Ltd
Official description
Verbatim source text
Permission at the Maldron Hotel, 93-95 South Mall, 17-18 Parnell Place, and Beasley Street, Cork. The proposed development will consist of a change of uses in Nos. 17 and 18 Parnell Place, which are Protected Structures (Refs PS823 and PS822), from the permitted but unimplemented ground floor retail use to a hotel office and administrative use. The proposed development also includes minor exterior works consisting of the renewal/restoration of existing fascia cornice.
Verify against official sourceMore Cork planning activity
These are county discovery links, not claimed relationships to this application.
Project team
Named source parties
- Promoter
- Dalata Hotel Group Plc
- Planning agent
- Summerhill Construction Co Ltd
- Builder / developer
- Summerhill Construction Co Ltd
Lifecycle timeline
Application to site progress
-
Appeal
No appeal indexed No public appeal record is indexed against this application. -
Completed
Completion certificate recorded CC00000060286CY · commencement CN0135679CY · recorded in Nov 2025 · 1 unit on this certificate The month is when the certificate appeared in the indexed source, not a separate completion date. The source does not state whether this is full or partial completion. Certificate units are not summed with other certificates or planning totals. Completion evidence projection checked 2 Aug 2026.