Planning record · Co. Donegal

Pairc tionsclaiochta ui dhomhnaill, an curraoin, an tearmann, Co. Donegal

Granted 18 Jan 2018 (final grant issued 21 Feb 2018)

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Donegal by email

Key facts

  • Planning application 1751767 at Pairc Tionsclaiochta Ui Dhomhnaill, An Curraoin, An Tearmann, Co. Donegal: Síneadh a chuir leis an bhfoirgneamh atá ann cheana féin chun rothair…
  • It was received by Donegal County Council on 22 Nov 2017.
  • Status: Granted 18 Jan 2018 (final grant issued 21 Feb 2018).
  • Work was due to start on 12 Oct 2018, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Donegal County Council planning register, as last seen on 2 Jun 2026. Open the council's file

Planning applications in Co. Donegal

Council register

The council's register shows: Granted on 18 Jan 2018.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Síneadh a chuir leis an bhfoirgneamh atá ann cheana féin chun rothair…

SÍNEADH A CHUIR LEIS AN BHFOIRGNEAMH ATÁ ANN CHEANA FÉIN CHUN ROTHAIR A CHOTHABHAIL CHOMH MAITH LE OBAIR EILE BAINTEACH LEIS AN SUÍOMH

Location
An Tearmann, Co. Donegal Map
Planning reference
1751767

Numbers and dates

Project type
Planning record
Received
22 Nov 2017
Decision to grant
18 Jan 2018
Final grant
21 Feb 2018
Site start notified
12 Oct 2018

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 12 Oct 2018, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 1751767 on eplanning.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Donegal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 12 Oct 2018Notice filed · Bike shop extension to existing Community centre at An Craoibhin TermonView the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near An Tearmann

Get alerts for Co. DonegalFree. We email you when new applications appear.

Free email alerts

Get new Donegal projects by email

New applications, decisions and site starts in Co. Donegal. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options