Site start · Co. Donegal
Letterkenny, Donegal
Site start 8 Mar 2021
Archived record
This application has left our current planning lists, so this page is no longer updated. We last saw it in the council's register on 12 Jul 2026. The details below are as they were then. The council's register has the current status.
Search the Donegal planning registerCurrent planning applications in Letterkenny
What and where
~94 homes
REVISIONS TO PREVIOUSLY APPROVED PLANNING REF. NO. 06/80149 AND EXTENDED UNDER PLANNING REF. NO'S 12/80073 & 17/51689: (1) REVISIONS TO PART OF INTERNAL SITE LAYOUT AND ALL ASSOCIATED SITE WORKS TO INCLUDE UPGRADING/REALIGNMENT OF KNOCKANAR ROAD AND CONNECTION TO EXISTING PUBLIC SEWER, (2) OMISSION OF 94 NO. RESIDENTIAL UNITS PREVIOUSLY APPROVED AND CONSTRUCTION OF 72 NO. DWELLINGS AND 16 NO. APARTMENTS (TOTAL NO. 88 RESIDENTIAL UNITS). RELOCATION OF CRÉCHE AND ASSOCIATED SITE WORKS
- Location
- Letterkenny, Co. Donegal Map
- Council
- Donegal County Council
- Planning reference
- 1851993
- Applicant
- GDC (Irl) Ltd
- Agent
- GDC (Irl) Ltd
Key facts
- Homes
- ~94estimated from the application
- Project type
- Large residential
- Site start
- 8 Mar 2021
Documents and evidence
Check the record
- Council planning fileThe application file 1851993 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Donegal County Council planning register, as last seen on 12 Jul 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 8 Mar 2021Work started · phase 1 · Construction of apartment block containing Nos. 30, 31, 32 & 33 (4 No. apartments)
- 30 Mar 2022Work started · phase 2 · Construction of apartment block
- 12 Oct 2024Work started · phase 3 · Construction of a new building containing 4 No.apartments 05, 06, 07 & 08
- 12 Oct 2024Work started · phase 4 · Construction of a new building containing 4 No.apartments - 01, 02, 03 & 04
- Completion certificate recordedRecorded in Mar 2021 · 4 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 30 Sep 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area