Large residential · Co. Donegal
Glencar scotch, letterkenny po, Co. Donegal
Granted on appeal 28 Sep 2020 (Decision to grant 26 Mar 2020 by the council)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Donegal by email
Key facts
- Planning application 1950809 at Glencar Scotch, Letterkenny Po, Co. Donegal: Housing development.
- It was received by Donegal County Council on 30 May 2019.
- Status: Granted on appeal 28 Sep 2020 (Decision to grant 26 Mar 2020 by the council).
Source: the Donegal County Council planning register, as last seen on 2 Jun 2026. Open the council's file
Council register
The council's register shows: Decision to grant on 26 Mar 2020.
Search the Donegal planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Housing development
CONSTRUCTION OF HOUSING DEVELOPMENT CONTAINING 20 NO. RESIDENTIAL UNITS AS FOLLOWS: (A) 8 NO. SEMI-DETACHED DWELLINGS AND (B) 12 NO. APARTMENTS CONFIGURED IN 2 SEPARATE BLOCKS OF 6 UNITS, EACH CONTAINING 4 NO. 2 BEDROOM AND 2 NO. 1 BEDROOM UNITS. THE PROPOSAL INCLUDES DEVELOPMENT OF INTERNAL ACCESS ROADWAY, PEDESTRIAN FOOTPATHS, INTERNAL COMMUNAL PLAY AND OPEN SPACE AREAS, BOUNDARY TREATMENTS, CONNECTION TO ALL MAIN SERVICES AND ASSOCIATED SITE DEVELOPMENT WORKS INCLUDING RE-DIVERTING EXISTING FOUL SEWER PIPEWORK WHICH TRAVERSES THE SITE
- Location
- Glencar Scotch, Co. Donegal Map
- Council
- Donegal County Council
- Planning reference
- 1950809
Numbers and dates
- Project type
- Large residential
- Received
- 30 May 2019
- Council decision
- 26 Mar 2020
- Appeal lodged
- 7 May 2020
- Granted on appeal
- 28 Sep 2020
- Site start notified
- 30 Jun 2021
Timeline
- Application received
- Decision to grant by the council
- Appeal lodged
- Appeal decidedGrant permission with revised conditions
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 1950809 on eplanning.ie: drawings, reports and the decision.Open the council's file
- AppealGrant permission with revised conditions · 307152 / 28 Sep 2020View the appeal record
How we know this
From the Donegal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 30 Jun 2021Notice filed · phase 1 · Construction of 8 no. semi-detached dwellings & all associated siteworks forming Phase 1...View the site start
- 21 Jan 2022Notice filed · phase 2 · Apartment Nos. 1-4, Ard Na Gréine, Glencar Scotch, Letterkenny, Co. Donegal...View the site start
- 15 Feb 2022Notice filed · phase 3 · Apartment Nos. 13-18, Ard Na Gréine, Glencar Scotch, Letterkenny, Co. Donegal...View the site start
- Completion certificate recordedRecorded in Jun 2021 · 8 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
- Completion certificate recordedRecorded in Jan 2022 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.