One-off house · Co. Donegal
Kilmacrennan road, knocknamona, letterkenny, Co. Donegal
Granted 10 Sep 2020 (final grant issued 14 Oct 2020)
We no longer update this application, so we can't email you about it. Get new planning applications in Letterkenny by email
Key facts
- Planning application 1951902 at Kilmacrennan Road, Knocknamona, Letterkenny, Co. Donegal: Part two storey, part three storey, community nursing…
- It was received by Donegal County Council on 9 Dec 2019.
- Status: Granted 10 Sep 2020 (final grant issued 14 Oct 2020).
- Work was due to start on 20 Nov 2023, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Donegal County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Letterkenny · Planning applications in Co. Donegal
Council register
The council's register shows: Granted on 10 Sep 2020.
Search the Donegal planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Part two storey, part three storey, community nursing…
CONSTRUCTION OF A PART TWO STOREY, PART THREE STOREY, COMMUNITY NURSING UNIT/RESIDENTIAL CARE UNIT (9,400 m² TOTAL GROSS FLOOR AREA). THE BUILDING COMPRISES OF 110 BEDS FOR A MIX OF LONG STAY, SHORT STAY/REHABILITATION AND DEMENTIA USES WITH ASSOCIATED RESIDENT ACCOMMODATION INCLUDING DINING ROOMS, KITCHENETTES, RESIDENT AREAS WITH FAMILY OVERNIGHT ROOM, VISITOR'S ROOM, TREATMENT ROOMS, HAIRDRESSER'S SALON; REHABILITATION ROOMS; INTERNAL COURTYARD AND TERRACE SPACES; BACK OF HOUSE AREAS INCLUDING KITCHEN AND LAUNDRY ROOMS, STAFF ACCOMMODATION AND ANCILLARY OFFICES AND NEW ENTRANCE FROM KILMACRENNAN ROAD; HARD AND SOFT LANDSCAPING; SERVICE YARD (THE TOTAL GROSS FLOOR AREA OF SERVICE BUILDINGS IS 74 m² AND INCLUDES WASTE STORAGE AREA, STAFF AREAS AND ESB SWITCH ROOM AND SUB STATION); AND ALL ASSOCIATED SITE AND DEVELOPMENT WORKS
- Location
- Letterkenny, Co. Donegal Map
- Council
- Donegal County Council
- Planning reference
- 1951902
Numbers and dates
- Homes
- ~1estimated from the application
- Floor area
- 9,400 m²
- Project type
- One-off house
- Received
- 9 Dec 2019
- Decision to grant
- 10 Sep 2020
- Final grant
- 14 Oct 2020
- Site start notified
- 20 Nov 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 1951902 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Donegal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 20 Nov 2023Notice filed · phase 1 · Construction of new 110 bed Community Nursing Home at Kilmacrennan Road, Knocknamona...View the site start
- 3 May 2024Notice filed · phase 2 · Proposed construction of new ESB substation building and waste compoundView the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.