Infrastructure · Co. Donegal
Altaghaderry, killea, lifford po, Co. Donegal
Granted 10 Sep 2020 (final grant issued 14 Oct 2020)
We no longer update this application, so we can't email you about it. Get new planning applications in Killea by email
Key facts
- Planning application 2050982 at Altaghaderry, Killea, Lifford Po, Co. Donegal: Upgrade works.
- It was received by Donegal County Council on 22 Jul 2020.
- Status: Granted 10 Sep 2020 (final grant issued 14 Oct 2020).
Source: the Donegal County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Killea · Planning applications in Co. Donegal
Council register
The council's register shows: Granted on 10 Sep 2020.
Search the Donegal planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Upgrade works
UPGRADE WORKS AT KILLEA WASTEWATER TREATMENT PLANT AS FOLLOWS: (1) NEW INLET WORKS (2) 2 NO. PRIMARY SETTLEMENT TANKS (3) STORMWATER HOLDING TANK AND STORMWATER RETURN PUMPING STATION (4) ROTATING BIOLOGICAL CONTRACTOR (RBC) UNITS (5) 2 NO. FINAL SETTLEMENT TANKS (6) NEW ADMINISTRATION BUILDING (6) SLUDGE STORAGE TANK (7) NEW SECURITY FENCE (8) SITE ROADS (9) DEMOLITION OF THE EXISTING ADMINISTRATION BUILDING (10) DECOMMISSIONING OF THE EXISTING SECONDARY TREATMENT UNITS (11) DECOMMISSIONING OF THE EXISTING INLET WORKS. A NATURA IMPACT STATEMENT (NIS) ACCOMPANIES THIS APPLICATION
- Location
- Killea, Co. Donegal Map
- Council
- Donegal County Council
- Planning reference
- 2050982
Numbers and dates
- Project type
- Infrastructure
- Received
- 22 Jul 2020
- Decision to grant
- 10 Sep 2020
- Final grant
- 14 Oct 2020
- Site start notified
- 21 Jul 2021
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 2050982 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Donegal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 21 Jul 2021Notice filed · Construction of single storey control building as part of the Waste Water Treatment PlantView the site start
- Completion certificate recordedRecorded in Jul 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.