Infrastructure · Co. Donegal
Quay road, dungloe, Co. Donegal
Granted 30 Sep 2021 (final grant issued 11 Nov 2021)
We no longer update this application, so we can't email you about it. Get new planning applications in Dungloe by email
Key facts
- Planning application 2151576 at Quay Road, Dungloe, Co. Donegal: Conversion of the former social welfare / dole office into new…
- It was received by Donegal County Council on 6 Aug 2021.
- Status: Granted 30 Sep 2021 (final grant issued 11 Nov 2021).
Source: the Donegal County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Dungloe · Planning applications in Co. Donegal
Council register
The council's register shows: Granted on 30 Sep 2021.
Search the Donegal planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Conversion of the former social welfare / dole office into new…
CONVERSION OF THE FORMER SOCIAL WELFARE / DOLE OFFICE INTO NEW APARTMENTS (5 NO. IN TOTAL) CONSISTING OF (A) CONSTRUCTION OF (1) 1 NO. 2-BEDROOM & 1 NO. 1-BEDROOM APARTMENTS AT GROUND FLOOR LEVEL (2) 1 NO. 2-BEDROOM & 1 NO. 1-BEDROOM APARTMENTS AT FIRST FLOOR LEVEL (3) MINOR EXTENSION (8.18 m²) TO EXISTING BUILDING AT FIRST FLOOR LEVEL TO NORTH EAST ELEVATION (4) THE ADAPTION / CONVERSION OF EXISTING ROOF LEVEL TO PROVIDE 1 NO. 2-BEDROOM PENTHOUSE APARTMENT (5) RESIDENT STORAGE AREAS AND FACILITIES AT BASEMENT / LOWER GROUND LEVEL (6) COMMUNAL GARDEN & PARKING SPACES (7) NEW ENTRANCE TO BUILDING AT GROUND FLOOR LEVEL (8) CHANGES TO EXISTING ELEVATIONS NAMELY NEW AND AMENDED WINDOWS & DOORS (B) INSTALLATION OF A DRAINAGE PUMPING STATION; ALONG WITH ASSOCIATED SITEWORKS AND CONNECTION TO EXISTING SERVICES
- Location
- Dungloe, Co. Donegal Map
- Council
- Donegal County Council
- Planning reference
- 2151576
Numbers and dates
- Floor area
- 364 m²
- Project type
- Infrastructure
- Received
- 6 Aug 2021
- Decision to grant
- 30 Sep 2021
- Final grant
- 11 Nov 2021
- Site start notified
- 20 Oct 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 2151576 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Donegal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 20 Oct 2023Notice filed · Material Alterations & Change of Use from Office to Guest AccomodationView the site start
- Completion certificate recordedRecorded in Oct 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.