One-off house · Co. Donegal
Kilraine upper, glenties, letterkenny po, Co. Donegal
Granted 12 Jan 2023 (final grant issued 20 Feb 2023)
We no longer update this application, so we can't email you about it. Get new planning applications in Glenties by email
Key facts
- Planning application 2251844 at Kilraine Upper, Glenties, Letterkenny Po, Co. Donegal: Demolition of a mica affected habitable dwelling.
- It was received by Donegal County Council on 14 Nov 2022.
- Status: Granted 12 Jan 2023 (final grant issued 20 Feb 2023).
Source: the Donegal County Council planning register, as last seen on 2 Jun 2026. Open the council's file
More planning applications in Glenties · Planning applications in Co. Donegal
Council register
The council's register shows: Granted on 12 Jan 2023.
Search the Donegal planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Demolition of a mica affected habitable dwelling
(1) DEMOLITION OF A MICA AFFECTED HABITABLE DWELLING (2) PROVISION OF FIRST FLOOR LIVING ACCOMMODATION AND STORAGE WITHIN AN EXISTING DETACHED SHED INCLUDING CONNECTION TO THE EXISTING WASTEWATER TREATMENT SYSTEM (3) RECONSTRUCTION OF THE ABOVE DWELLING WITH CONNECTION TO EXISTING WASTEWATER TREATMENT SYSTEM INCLUDING ALL ASSOCIATED SITE DEVELOPMENT WORKS
- Location
- Glenties, Co. Donegal Map
- Council
- Donegal County Council
- Planning reference
- 2251844
Numbers and dates
- Homes
- 1
- Floor area
- 322 m²
- Project type
- One-off house
- Received
- 14 Nov 2022
- Decision to grant
- 12 Jan 2023
- Final grant
- 20 Feb 2023
- Site start notified
- 19 Jun 2024
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning fileThe application file 2251844 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Donegal County Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 19 Jun 2024Notice filed · DEMOLITION OF A MICA AFFECTED DWELLING AND RECONSTRUCTIO N OF NEW DWELLING WITH...View the site start
- Completion certificate recordedRecorded in Jun 2024 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area