One-off house · Co. Donegal
Tirhomin, milford, letterkenny po, Co. Donegal
Granted 20 Mar 2025 (final grant issued 23 Apr 2025)
We no longer update this application, so we can't email you about it. Get new planning applications in Milford by email
Key facts
- Planning application 2450199 at Tirhomin, Milford, Letterkenny Po, Co. Donegal: Dwelling house.
- It was received by Donegal County Council on 4 Sep 2024.
- Status: Granted 20 Mar 2025 (final grant issued 23 Apr 2025).
- Work was due to start on 17 Sep 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Donegal County Council planning register, as last seen on 5 Oct 2026. Open the council's file
More planning applications in Milford · Planning applications in Co. Donegal
Council register
The council's register shows: Granted on 20 Mar 2025.
Search the Donegal planning register
Application details as we last saw them in the national register on 5 Oct 2026.
What and where
Dwelling house
ERECTION OF A DWELLING HOUSE, WITH WASTEWATER TREATMENT SYSTEM AND PERCOLATION AREA
- Location
- Milford, Co. Donegal Map
- Council
- Donegal County Council
- Planning reference
- 2450199
Numbers and dates
- Homes
- 1
- Floor area
- 348 m²
- Project type
- One-off house
- Received
- 4 Sep 2024
- Decision to grant
- 20 Mar 2025
- Final grant
- 23 Apr 2025
- Site start notified
- 17 Sep 2025
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning fileThe application file 2450199 on eplanning.ie: drawings, reports and the decision.Open the council's file
How we know this
From the Donegal County Council planning register, as last seen on 5 Oct 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 17 Sep 2025Notice filed · ERECTION OF A DWELLING HOUSE, WITH WASTEWATER TREATMENT SYSTEM AND PERCOLATION AREAView the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.