Commencement

Commercial fit-out, Burnfoot, Donegal - Planning Application 2461131

Donegal / Burnfoot / Burnfoot, Donegal

Est. value Not listed
Units Not listed
Floor area Not listed
Commenced 13 May 2025

Source-linked planning record

Commercial fit-out, Burnfoot, Donegal - Planning Application 2461131

Donegal / Burnfoot / Burnfoot, Donegal
PB ref
PB-159907
Plan ref
2461131
Authority
Donegal County Council
Stage / date
Commencement / 13 May 2025
Est. value band
Value not disclosed
Project class
Commercial fit-out
Promoter
not available yet
Architect / agent
Dunwoody & Dobson Ltd

Source: http://www.eplanning.ie/DonegalCC/AppFileRefDetails/2461131/0

Key facts

Lead summary

Source
Owner-supplied commencement export
Planning authority
Donegal County Council
Application reference
2461131
Applicant
not available yet
Agent
Dunwoody & Dobson Ltd
Decision stage
Commencement
Commenced
13 May 2025
Builder / developer
Dunwoody & Dobson Ltd

Official description

Verbatim source text

(1) CHANGE OF USE OF CERAMIC TILE SHOWROOM PERMITTED UNDER PLANNING REF. NO. 19/51974 AND UNOCCUPIED STORAGE AREA PERMITTED UNDER PLANNING REF. NO. 16/51631 TO DELIVERY SERVICE OFFICE FOR AN POST TO FACILITATE THE RECEIPT, SORTATION AND PROCESSING OF MAILS AND PARCELS FOR ONWARD DELIVERY AND (2) ADDITIONAL CAR PARKING FACILITIES TO FACILITATE EV CHARGING FOR DELIVERY VANS INCLUDING BOUNDARY FENCING AND CAR PARK LIGHTING WITH CONNECTION TO EXISTING SERVICES AND ALL ASSOCIATED SITE DEVELOPMENT WORKS

Verify against official source

Project team

Named source parties

Promoter
not available yet
Planning agent
Dunwoody & Dobson Ltd
Builder / developer
Dunwoody & Dobson Ltd

Lifecycle timeline

Application to site progress

  1. Applied

    13 May 2025 2461131
  2. Decision

    Commencement notice filed 13 Sep 2024
  3. Appeal

    No appeal indexed No public appeal record is indexed against this application.
  4. Commenced

    13 May 2025 CN0128552DL
  5. Completed

    Completion certificate recorded CC00000057117DL · commencement CN0128552DL · recorded in May 2025 · 1 unit on this certificate The month is when the certificate appeared in the indexed source, not a separate completion date. The source does not state whether this is full or partial completion. Certificate units are not summed with other certificates or planning totals. Completion evidence projection checked 5 Aug 2026.

Likely trades & supplier leads

Inferred from scheme type and scale

ElectricalFit-outSignageSolar/EnergyHealth & Safety