Commercial fit-out, Burnfoot, Donegal - Planning Application 2461131
Donegal / Burnfoot / Burnfoot, Donegal
Source-linked planning record
Commercial fit-out, Burnfoot, Donegal - Planning Application 2461131
Donegal / Burnfoot / Burnfoot, Donegal- PB ref
- PB-159907
- Plan ref
- 2461131
- Authority
- Donegal County Council
- Stage / date
- Commencement / 13 May 2025
- Est. value band
- Value not disclosed
- Project class
- Commercial fit-out
- Promoter
- not available yet
- Architect / agent
- Dunwoody & Dobson Ltd
Source: http://www.eplanning.ie/DonegalCC/AppFileRefDetails/2461131/0
Key facts
Lead summary
- Source
- Owner-supplied commencement export
- Planning authority
- Donegal County Council
- Application reference
- 2461131
- Applicant
- not available yet
- Agent
- Dunwoody & Dobson Ltd
- Decision stage
- Commencement
- Commenced
- 13 May 2025
- Builder / developer
- Dunwoody & Dobson Ltd
Official description
Verbatim source text
(1) CHANGE OF USE OF CERAMIC TILE SHOWROOM PERMITTED UNDER PLANNING REF. NO. 19/51974 AND UNOCCUPIED STORAGE AREA PERMITTED UNDER PLANNING REF. NO. 16/51631 TO DELIVERY SERVICE OFFICE FOR AN POST TO FACILITATE THE RECEIPT, SORTATION AND PROCESSING OF MAILS AND PARCELS FOR ONWARD DELIVERY AND (2) ADDITIONAL CAR PARKING FACILITIES TO FACILITATE EV CHARGING FOR DELIVERY VANS INCLUDING BOUNDARY FENCING AND CAR PARK LIGHTING WITH CONNECTION TO EXISTING SERVICES AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
Verify against official sourceMore Donegal planning activity
These are county discovery links, not claimed relationships to this application.
Project team
Named source parties
- Promoter
- not available yet
- Planning agent
- Dunwoody & Dobson Ltd
- Builder / developer
- Dunwoody & Dobson Ltd
Lifecycle timeline
Application to site progress
-
Appeal
No appeal indexed No public appeal record is indexed against this application. -
Completed
Completion certificate recorded CC00000057117DL · commencement CN0128552DL · recorded in May 2025 · 1 unit on this certificate The month is when the certificate appeared in the indexed source, not a separate completion date. The source does not state whether this is full or partial completion. Certificate units are not summed with other certificates or planning totals. Completion evidence projection checked 5 Aug 2026.