Demolition · Co. Dublin
68, Ennafort Park, Raheny, Dublin 5
Granted 23 Mar 2021 (final grant issued 6 May 2021)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 5 by email
Key facts
- Planning application 2104/21 at 68, Ennafort Park, Raheny, Dublin 5: Demolition of the existing garage to the side & front.
- It was received by Dublin City Council on 28 Jan 2021.
- Status: Granted 23 Mar 2021 (final grant issued 6 May 2021).
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 5 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 23 Mar 2021.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Demolition of the existing garage to the side & front
RETENTION AND PERMISSION: Permission for the demolition of the existing garage to the side & front, the construction of a two storey extension to the side & front with 3 roof lights in the side hip of the extended main roof, the construction of a single storey extension to the rear, the widening of the existing vehicular entrance and associated site works. Retention permission is sought for a dormer roof extension on the rear slope and a rooflight on the front slope of the main roof.
- Location
- Dublin 5, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 2104/21
- Application type
- Retention permission
Numbers and dates
- Project type
- Demolition
- Received
- 28 Jan 2021
- Decision to grant
- 23 Mar 2021
- Final grant
- 6 May 2021
- Site start notified
- 5 Jul 2021
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 2104/21.Search the register
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 5 Jul 2021Notice filed · Extension to the side and rear of 68 Ennafort Park, Raheny, Dublin 5 and associated site...View the site start
- Completion certificate recordedRecorded in Jul 2021 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.