Infrastructure · Co. Dublin
Lands at the corner of Oliver Bond Street and St. Augustine Street, (Mullinahack) Christchurch, Dublin 8
Granted 13 Jul 2020
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 8 by email
Key facts
- Planning application 2295/20 at Lands At The Corner of Oliver Bond Street and St. Augustine Street, (Mullinahack) Christchurch, Dublin 8: Infrastructure works.
- It was received by Dublin City Council on 18 Feb 2020.
- Status: Granted 13 Jul 2020.
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 8 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 13 Jul 2020.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Infrastructure works
The proposed development, which provides for alterations to the permitted building, comprises the change of use from permitted aparthotel with ancillary facilities, to proposed hotel and ancillary facilities, (including fully licensed public bar/restaurant, reception/foyer area, laundry, storage, staff facilities, ESB substation/switchroom), internal alterations on all floors and extensions to the permitted ground and basement level. The development also comprises internal alterations to all floors, including the reconfiguration of: bedrooms (resulting in a 95 no. bedroom hotel, an increase of 24 no. bedrooms, including 2 no. bedrooms at basement level and 2 no. at ground floor level); circulation and cores; the introduction of a lightwell to basement level; alterations to the main entrance, plant and back of house areas, including the bin store and cycle parking. The scheme also includes: elevational changes; and associated alterations to the permitted scheme's services (mechanical and electrical, water supply, sewage disposal and surface water disposal). The resultant overall gross floor area of the proposed building will increase to 2,531 sq m (including internal plant, extensions at basement (total gross floor area proposed 156 sq m) and ground floor (total gross floor level proposed 338 sq m) levels.
- Location
- Dublin 8, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 2295/20
Numbers and dates
- Floor area
- 24 m²
- Project type
- Infrastructure
- Received
- 18 Feb 2020
- Granted
- 13 Jul 2020
- Site start
- 2 May 2023
Timeline
- Application received
- Granted
- Site start
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 2295/20.Search the register
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 2 May 2023Work started · Construction of an eight storey hotel over basement at Oliver Bond Street, Dublin.View the site start
- Completion certificate recordedRecorded in May 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 26 Oct 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.