Planning record · Co. Dublin
50, Shanboley Road, Beaumont, Dublin 9
Granted 26 Apr 2019 (final grant issued 6 Jun 2019)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 9 by email
Key facts
- Planning application 2406/19 at 50, Shanboley Road, Beaumont, Dublin 9: Widen existing vehicular entrance to 3.3m wide and to construct new…
- It was received by Dublin City Council on 4 Mar 2019.
- Status: Granted 26 Apr 2019 (final grant issued 6 Jun 2019).
- Work was due to start on 26 Jul 2019, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 9 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 26 Apr 2019.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Widen existing vehicular entrance to 3.3m wide and to construct new…
Planning permission to widen existing vehicular entrance to 3.3m wide and to construct new 1st floor extension to side over existing garage also single storey ground floor extension to rear incorporating attic conversion to storage room, bedroom and bathroom at 1st floor also kitchen dining room at ground floor, internal alterations and all associated site works at 50 Shanboley Road, Beaumont, Dublin 9.
- Location
- Dublin 9, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 2406/19
Numbers and dates
- Project type
- Planning record
- Received
- 4 Mar 2019
- Decision to grant
- 26 Apr 2019
- Final grant
- 6 Jun 2019
- Site start notified
- 26 Jul 2019
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 2406/19.Search the register
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 26 Jul 2019Notice filed · To widen existing vehicular entrance to 3.0m wide and to construct new 1st floor...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.