Large residential · Co. Dublin

Capel Site, Pelletstown, Ashtown, Dublin 15

Under appeal since 21 Oct 2020 (Granted 2 Oct 2020 by the council)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 15 by email

Key facts

  • Planning application 2596/20 at Capel Site, Pelletstown, Ashtown, Dublin 15: Site forms part of the wider ‘Capel’ site.
  • It was received by Dublin City Council on 30 Mar 2020.
  • Status: Under appeal since 21 Oct 2020 (Granted 2 Oct 2020 by the council).

Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register

More planning applications in Dublin 15 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 2 Oct 2020.

Appealed to An Coimisiún Pleanála on 21 Oct 2020.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Site forms part of the wider ‘Capel’ site

Permission for development at a site (c.1.66 Ha) known as the ‘Capel’ site, Pelletstown, Ashtown, Dublin 15. The site forms part of the wider ‘Capel’ site, and is bounded generally by Rathborne Avenue to the north and west, existing residential development adjoining Rathborne Drive and Royal Canal Way to the east and the remainder of the development permitted under DCC Reg. Ref. 3666/15 (ABP Ref PL29N.246373) to the south, at Pelletstown, Ashtown, Dublin 15. The development will consist of minor amendments to the development permitted under DCC Reg. Ref. 3666/15 (ABP Ref PL29N.246373) comprising changes to house types to 92 dwellings as follows: 25no. 2 storey, 3 bedroom house type units each of c. 105.3sq.m (Types HAL, HA, HALM, HAM and HAR) to replace 25no. house type C units (2 storey, 3 bedroom); 17no. 3 storey, 4 bedroom house type units of c. 150.8sq.m (Types HB and HBM) to replace 12no. house type F units (3 storey, 4 bedroom) and 5no. 2 storey, 3 bedroom house type D units; 22no. 3 storey, 4 bedroom house type units each of c. 153.2sq.m (Types HCL, HC, HCM and HCR) to replace 22no. house type E units (3 storey, 4 bedroom); 10no. 3 storey, 4 bedroom house type units of c. 167.5sq.m (Types HDL and HDR) to replace 6no. house type K units (3storey, 4 bedroom), 1no. house type B unit (2 storey, 3 bedroom) and 3no. house type A units (2 storey, 3 bedroom); 18no. 2 storey, 3 bedroom house type units each of c. 102.8sq.m (type HEL, HELM, HERM and HER) to replace 6no.house type K units (3 storey, 4 bedroom) and 12no. house type A units (2 storey, 3 bedroom). A new substation (c. 11.5 m²) is also proposed with associated drop kerb access. All houses will include solar panels on the roofs, as previously permitted. Some minor changes to the arrangement of car parking spaces associated with the amendments to the 92 houses are also proposed. The amendments will not impact on the permitted street layout or overall number of houses permitted under DCC Reg. Ref. 3666/15 (ABP PL29N.246373).

Location
Dublin 15, Co. Dublin Map
Planning reference
2596/20

Numbers and dates

Project type
Large residential
Received
30 Mar 2020
Council decision
2 Oct 2020
Appeal lodged
21 Oct 2020
Site start notified
29 Jul 2021

Timeline

  1. Application received
  2. Granted by the council
  3. Appeal lodged
  4. Site start notified

Documents and evidence

Check the record

How we know this

From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 29 Jul 2021Notice filed · phase 1 · Enabling works only to the proposed Rathborne Site for development consisting of...View the site start
  2. 13 Oct 2021Notice filed · phase 2 · Residential Development at Rathborne, consisting of 92 No. housing units and all...View the site start
  3. Completion certificate recordedRecorded in Oct 2021 · 20 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  4. Completion certificate recordedRecorded in Oct 2021 · 16 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
  5. Completion certificate recordedRecorded in Oct 2021 · 12 units on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 15

Get alerts for Dublin 15Free. We email you when new applications appear.

Free email alerts

Get new Dublin 15 projects by email

New applications, decisions and site starts in Dublin 15, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options