One-off house · Co. Dublin

Rear of 388 Collins Avenue, Whitehall, Dublin 9 D09 F6T8

Granted 23 Jun 2021

We no longer update this application, so we can't email you about it. Get new planning applications in Co. Dublin by email

Key facts

  • Planning application 2691/21 at Rear of 388 Collins Avenue, Whitehall, Dublin 9 D09 F6T8: Demolition of 3 no. existing single storey garages/ outhouses…
  • It was received by Dublin City Council on 29 Apr 2021.
  • Status: Granted 23 Jun 2021.
  • Work started on site on 3 Aug 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Dublin City Council planning register, as last seen on 13 Oct 2026. Open the council's file

Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 23 Jun 2021.

Application details as we last saw them in the national register on 13 Oct 2026.

What and where

Demolition of 3 no. existing single storey garages/ outhouses…

Permission sought for demolition of 3 no. existing single storey garages/ outhouses to the rear yard area and for the construction of a single residential end of terrace mews dwelling on the same site with 4 bedrooms and 3 stories in height (to include attic space). Proposed house to front onto the laneway behind with access via the existing side laneway off Collins Avenue. Application to include widening of the existing side laneway to 5, 5m by way of reduction in applicant's site width, new pedestrian gate inside boundary wall to access rear garden, off street parking for 1 car, dormer type windows to the south & north elevations at attic level and all associated site development works and services connections.

Location
Dublin 9 D09 F6t8, Co. Dublin Map
Planning reference
2691/21
Application type
Permission

Numbers and dates

Homes
~1estimated from the application
Project type
One-off house
Received
29 Apr 2021
Granted
23 Jun 2021
Site start
3 Aug 2026

Timeline

  1. Application received
  2. Granted
  3. Site start

Outlook

What happens next

Work started on site on 3 Aug 2026, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

Work packages named so far

  • Roads and site development worksNamed in the application description
  • Services and drainageNamed in the application description

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning fileThe application file 2691/21 on planning.agileapplications.ie: drawings, reports and the decision.Open the council's file

How we know this

From the Dublin City Council planning register, as last seen on 13 Oct 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 3 Aug 2026Work started · Demolition of existing garages and construction of new 4 bed houseView the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 9 D09 F6t8

Get alerts for Co. DublinFree. We email you when new applications appear.

Free email alerts

Get new Dublin projects by email

New applications, decisions and site starts in Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options