Infrastructure · Co. Dublin
Carriglea Industrial Estate, Muirfield Drive, Naas Road, Dublin 12
Granted 5 Jul 2021 (final grant issued 20 Aug 2021)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 12 by email
Key facts
- Planning application 2812/21 at Carriglea Industrial Estate, Muirfield Drive, Naas Road, Dublin 12: Installation of solar photovoltaic modules and heat pump units…
- It was received by Dublin City Council on 21 May 2021.
- Status: Granted 5 Jul 2021 (final grant issued 20 Aug 2021).
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 12 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 5 Jul 2021.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Installation of solar photovoltaic modules and heat pump units…
The development will consist of 1) the installation of solar photovoltaic ('PV') modules and heat pump units on the roof of apartment building Block AC and solar photovoltaic ('PV') modules on the roof of apartment building Block B on the site; 2) the construction of a single storey substation building adjacent to the eastern boundary of the site to the east of apartment building Block F and the north of apartment building Block G and; 3) the construction of a louvered generator enclosure adjacent to the all-weather multi games area in the eastern part of the site to the south east of apartment buildings Block AC and Block B.
- Location
- Dublin 12, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 2812/21
Numbers and dates
- Project type
- Infrastructure
- Received
- 21 May 2021
- Decision to grant
- 5 Jul 2021
- Final grant
- 20 Aug 2021
- Site start notified
- 1 Mar 2023
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 2812/21.Search the register
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 1 Mar 2023Notice filed · Proposed construction of an ESB Substation and Switch Room at Castleview, Muirfield...View the site start
- Completion certificate recordedRecorded in Mar 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 20 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.