Energy · Co. Dublin
144, Thomas Street, Dublin 8
Granted 29 Jul 2019 (final grant issued 9 Sep 2019)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 8 by email
Key facts
- Planning application 2903/19 at 144, Thomas Street, Dublin 8: Removal of an existing faux shopfront to unoccupied site fronting…
- It was received by Dublin City Council on 2 May 2019.
- Status: Granted 29 Jul 2019 (final grant issued 9 Sep 2019).
- Work was due to start on 19 Sep 2019, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 8 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 29 Jul 2019.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Removal of an existing faux shopfront to unoccupied site fronting…
The proposed development consists of: (i) removal of an existing faux shopfront to unoccupied site fronting on to Thomas Street; (ii) partial removal of front boundary wall to Thomas Street; (iii) partial demolition of walls associated with previously existing building on site; (iv) construction of single storey ESB substation (37sq.m); (v) construction of new boundary wall, inclusive of vehicular entrance gate to Thomas Street; and (vi) all ancillary works necessary to facilitate the development. Permission is sought for a temporary permission of 5 no. years.
- Location
- Dublin 8, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 2903/19
Numbers and dates
- Floor area
- 37 m²
- Project type
- Energy
- Received
- 2 May 2019
- Decision to grant
- 29 Jul 2019
- Final grant
- 9 Sep 2019
- Site start notified
- 19 Sep 2019
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 2903/19.Search the register
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 19 Sep 2019Notice filed · Construction of single storey ESB substation (37sq.m); (v) construction of new boundary...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.