Commercial fit-out · Co. Dublin
Demolition of an existing single-storey pitched roofed light…, Dublin 8, Co. Dublin
Granted on appeal 14 Jan 2022 (Granted 22 Jan 2021 by the council)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 8 by email
Key facts
- Planning application 2915/20 at Dublin 8, Co. Dublin: Demolition of an existing single-storey pitched roofed light…
- It was received by Dublin City Council on 25 Jun 2020.
- Status: Granted on appeal 14 Jan 2022 (Granted 22 Jan 2021 by the council).
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 8 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 22 Jan 2021.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Demolition of an existing single-storey pitched roofed light…
Planning permission for development at a c. 0.1918 ha site at 36 Bride Street, Dublin 8, D08 AX62 and Molyneux House, 67-69 Bride Street, Dublin 8, D08 C8CN. The development will consist of the following; 1) The demolition of an existing single-storey pitched roofed light industrial building (c. 480 m²) and a 2/4/5-storey office building including the remaining external walls and roof of Molyneux Chapel (c. 2,639 m²); 2) The construction of a 247-room hotel building comprising of a part 4-storey, part 5-storey brickwork and polyester-powder coated framed glazed block facing Bride Street and a nine storey brickwork and polyester-powder coated framed glass block at the corner of Bride Street and Peter Street. A total of 14 disability accessible bedrooms are included; 3) The proposed building has a total height of 31.856m above ground (+44.41m ODM, including lift overrun), stepping back at 4th, 5th and 6th floor levels with a gross floor area of c. 8,326 m² (including basement of c. 261 m²); 4) The retention of a 4-storey brick facade element to Bride Street to create an 'art-link' open air gallery space at ground floor level and the insertion of a linked gallery 'Stephenson Room' at 2nd floor level; 5) Polyester powder-coated steel entrance gates, cycle parking stands both inside and outside gates and hard and soft landscaping elements and external seating to the existing terrace courtyard at the northern boundary of the site; 6) A ground floor 'Living Room' foyer area will include a bar and servery, check-in pods, soft seating areas and meeting rooms, toilets and back of house areas with links to the open air gallery and landscaped terrace courtyard. This area will span the entire width of the building on Bride Street and include side hung glazed terrace doors as well as a draught lobby with 2 no. sets of bi-parting automated doors; 7) An electrical sub-station located at ground floor on the Peter Street facade; 8) An existing part basement area is proposed to be retained for plant; 9) Rooftop plant areas above both 5th floor and 9th floor areas will be screened with polyester powder-coated louvered metal panels; 10) Artwork poem at 3rd, 4th and 5th floor levels to brickwork panel to Bride Street corner of the Peter Street facade; 11) 2 no. signage panels at 9th floor level to brick panels; 12) All other engineering and associated site development works.
- Location
- Dublin 8, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 2915/20
Numbers and dates
- Floor area
- 8,587 m²
- Estimated construction value
- €31m to €45mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Commercial fit-out
- Received
- 25 Jun 2020
- Council decision
- 22 Jan 2021
- Appeal lodged
- 16 Feb 2021
- Granted on appeal
- 14 Jan 2022
- Site start
- 8 Aug 2023
Timeline
- Application received
- Granted by the council
- Appeal lodged
- Appeal decidedGrant permission with revised conditions
- Site start
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 2915/20.Search the register
- AppealGrant permission with revised conditions · 309466 / 14 Jan 2022View the appeal record
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 8 Aug 2023Work started · Construction of a new 245 bedroom 9-storey hotel building. The works include the...View the site start
- Partial completion certificate recordedRecorded in Aug 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. It covers part of the development, not the whole permission. Units on this certificate are not added to other certificates or to the planning total. Last checked 26 Oct 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.