Infrastructure · Co. Dublin
75-78 Cork Street, Dublin 8
Granted 8 Mar 2024 (final grant issued 10 Apr 2024)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 8 by email
Key facts
- Planning application 3068/24 at 75-78 Cork Street, Dublin 8: Modifications to a mixed-use development permitted under Reg. Ref…
- It was received by Dublin City Council on 19 Jan 2024.
- Status: Granted 8 Mar 2024 (final grant issued 10 Apr 2024).
- Work was due to start on 14 Jun 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 8 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 8 Mar 2024.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Modifications to a mixed-use development permitted under Reg. Ref…
Modifications to a mixed-use development permitted under Reg. Ref. 3619/18 (as extended by Reg. Ref. 3619/18/X1) at No. 75-78 Cork Street, Dublin 8. The application site comprises of c.0.02 hectares and is bound by Cork Street to the south east, No. 79 Cork Street to the east, No. 74 Cork Street to the south-west and Our Lady's Road and Rosary Road to the north-west. The modifications proposed to the permitted scheme include relocation of the permitted ESB substation within the development in order to facilitate service access from Our Lady's Road. The modification also includes the provision of a meter room associated with the substation and alterations to the permitted pedestrian access, landscaping and carparking within the development. All other elements of the permitted development will remain unchanged and the development will be otherwise carried out in accordance with parent permission Reg. Ref. 3619/18 as extended.
- Location
- Dublin 8, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 3068/24
Numbers and dates
- Project type
- Infrastructure
- Received
- 19 Jan 2024
- Decision to grant
- 8 Mar 2024
- Final grant
- 10 Apr 2024
- Site start notified
- 14 Jun 2024
Timeline
- Application received
- Decision to grant
- Appeal lodged
- Appeal decidedInvalid- no acknowledgement of local submission S.127(1)e
- Final grant issued
- Site start notified
Site history
This site's history
-
Earlier planning reference 3619/18, named in this application's description: commencement notice filed for a start on 16 Aug 2021.
Erection of a 7-storey over Basement brick clad concrete structure multi-unit Residential Apartment Building (54 no units) with balconies… Named in this application's description
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 3068/24.Search the register
- AppealInvalid- no acknowledgement of local submission S.127(1)e · 319455 / 4 Apr 2024View the appeal record
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 14 Jun 2024Notice filed · Re-location of an ESB Sub-Station, as part of an overall mixed use development at 75-77...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.