Planning record · Co. Dublin
5, High Street, Christchurch, Dublin 8
Granted 18 Jul 2019 (final grant issued 30 Aug 2019)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 8 by email
Key facts
- Planning application 3081/19 at 5, High Street, Christchurch, Dublin 8: Extension to the existing office.
- It was received by Dublin City Council on 24 May 2019.
- Status: Granted 18 Jul 2019 (final grant issued 30 Aug 2019).
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 8 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 18 Jul 2019.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Extension to the existing office
Permission is being sought for development comprising construction of extension to the existing office at the first and second floor of 107.1 m² each, and construction of additional floor (proposed new third floor) with area of 342.9 m², with a proposed flat roof (total area of development 557.0 m²). -Elevational treatment to the front including: new glazed curtain walling with aluminium feature fins, over cladding part of the existing front elevation. -Internal alterations within existing warehouse for temporary office accommodation for the duration of construction. -Construction of a temporary escape stair on to Borris Court to the rear of existing warehouse for the duration of construction. And all associated site works. The building is located in a conservation area and Liberties Strategic Development and Regeneration area (SDRA 16).
- Location
- Dublin 8, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 3081/19
Numbers and dates
- Floor area
- 557 m²
- Project type
- Planning record
- Received
- 24 May 2019
- Decision to grant
- 18 Jul 2019
- Final grant
- 30 Aug 2019
- Site start notified
- 4 Feb 2020
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Site history
This site's history
-
Application WEB3230/26 at the same address: decision to grant 2 Nov 2026.
CHANGE OF USE. The development will consist of change of use of existing first floor mezzanine storage within the warehouse to proposed… Same address
Earlier records are the planning references this application names, records at the same address, and records within 50 m of the same map point. An address or a map point can cover more than one property, so check the council's file before relying on a match.
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 3081/19.Search the register
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 4 Feb 2020Notice filed · Extension to existing office first and second floor and construction of additional...View the site start
- Completion certificate recordedRecorded in Feb 2020 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 24 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.
Explore the area