Planning record · Co. Dublin

59 The Green, Beaumont Woods, Dublin 9, D09T882

Granted 18 Jun 2025 (final grant issued 23 Jul 2025)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 9 by email

Key facts

  • Planning application 3186/25 at 59 The Green, Beaumont Woods, Dublin 9, D09T882: Hip build up.
  • It was received by Dublin City Council on 1 May 2025.
  • Status: Granted 18 Jun 2025 (final grant issued 23 Jul 2025).
  • Work was due to start on 21 Aug 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Dublin City Council planning register, as last seen on 5 Oct 2026. Search the council's register

More planning applications in Dublin 9 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 18 Jun 2025.

Application details as we last saw them in the national register on 5 Oct 2026.

What and where

Hip build up

The development consists of hip build up at attic level into gable end with window in gable wall, dormer roof window on rear slope of roof and attic conversion to habitable room. Internal alterations at first floor.

Location
Dublin 9, Co. Dublin Map
Planning reference
3186/25

Numbers and dates

Project type
Planning record
Received
1 May 2025
Decision to grant
18 Jun 2025
Final grant
23 Jul 2025
Site start notified
21 Aug 2025

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 21 Aug 2025, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 3186/25.Search the register

How we know this

From the Dublin City Council planning register, as last seen on 5 Oct 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 21 Aug 2025Notice filed · Hip build up at attic level into gable end with window in gable wall. Dormer roof window...View the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 9

Get alerts for Dublin 9Free. We email you when new applications appear.

Free email alerts

Get new Dublin 9 projects by email

New applications, decisions and site starts in Dublin 9, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options