Mixed use · Co. Dublin
17-19 Richmond Street South and 14 Gordon Place, Dublin 2, D02 EF 20.
Granted 27 Jan 2022 (final grant issued 10 Mar 2022)
We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 2 by email
Key facts
- Planning application 3546/21 at 17-19 Richmond Street South and 14 Gordon Place, Dublin 2, D02 EF 20.: 22 homes.
- It was received by Dublin City Council on 23 Sep 2021.
- Status: Granted 27 Jan 2022 (final grant issued 10 Mar 2022).
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 2 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 27 Jan 2022.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
22 homes
For development at this site at 17-19 Richmond Street South and 14 Gordon Place, Dublin 2, D02 EF 20. The development (site area of 0.056 hectares) comprises lands currently occupied by the existing buildings of 18 & 19 Richmond St. South which are approved for demolition under Grant of permission DCC Reg. Ref. 4059/18. The proposed development will consist of the demolition of an additional 2 no. existing structures and construction of a new mixed-use development, 'The Gatehouse'. The proposal will provide for a building ranging in height from 6-storeys (max. parapet height 21.025 m) over ground-level fronting onto Richmond St. South and 7-storeys (max. parapet height 23.8m) over ground-level to the rear with a cumulative Gross Floor Area of 2,341 m². The development will consist of: Demolition of 2 no. existing structures (total GFA 195 m²) comprising; • a derelict structure adjoining 18/19 Richmond St. South to the north, and • a derelict structure positioned to the rear of 18/19 Richmond St. South along the southern site boundary. Construction of a new building comprising; • 2 no. retail units with a cumulative GFA of 244 sq.m consisting of Unit A (GFA 157sq.m) and Unit B (GFA 87 sq.m) at ground-floor level; • 22 no. apartment units at first-floor to seventh-floor level consisting of 11 no. 1- bedroom units and 11 no. 2-bedroom units; • a bin/plant room at ground-floor level with a GFA of 78.6 sq.m.; and • communal open space totalling 132 m² at sixth-floor (roof) level. All ancillary site works including site development including site clearance, drainage, and landscaping. The proposed development will be served by a total of 11 no. car-parking spaces and 44 no. bicycle parking spaces located in the basement of the adjacent block known as 'Block 5' which forms part of the wider development.
- Location
- Dublin 2, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 3546/21
Numbers and dates
- Homes
- 22
- Floor area
- 2,341 m²
- Estimated construction value
- €5.6m to €7.3mOur estimate from floor area and project type, at January 2026 prices, building works only. Not a stated figure. How we estimate
- Project type
- Mixed use
- Received
- 23 Sep 2021
- Decision to grant
- 27 Jan 2022
- Final grant
- 10 Mar 2022
- Site start notified
- 13 Dec 2022
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 3546/21.Search the register
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Site starts and completion
- 13 Dec 2022Notice filed · phase 1 · Demolition of existing buildings (No. 18/19 Richmond Street South) and enabling works to...View the site start
- 13 Feb 2023Notice filed · phase 2 · This Commencement Notice relates to a single stair residential building with 6 stories...View the site start
- Completion certificate recordedRecorded in Feb 2023 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.