  • Planning application 3647/19 at Former Gardener's Cottage, The Royal Hospital, Bloomfield Avenue, Donnybrook, Dublin 4: Change of use.
  • It was received by Dublin City Council on 31 Jul 2019.
  • Status: Granted 24 Sep 2019 (final grant issued 6 Nov 2019).

Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register

More planning applications in Dublin 4 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 24 Sep 2019.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Change of use

Permission at the former Gardener's Cottage, at the Royal Hospital Donnybrook, Bloomfield Avenue, Donnybrook, Dublin 4, D04 P8N6. The development consists of: permission for a change of use at the former Gardener's Cottage (c. 103 sq m) to a G.P. Practice comprising 3 no. consultation rooms, a minor procedures room, nurses' room, patient waiting room, reception, entrance lobby, shower room and toilet facilities (including disabled facilities) and minor ancillary site works.

Location
Dublin 4, Co. Dublin Map
Planning reference
3647/19

Numbers and dates

Floor area
103 m²
Project type
Public / civic
Received
31 Jul 2019
Decision to grant
24 Sep 2019
Final grant
6 Nov 2019
Site start notified
11 Aug 2020

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 3647/19.Search the register

How we know this

From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Site starts and completion

  1. 11 Aug 2020Notice filed · Internal alterations to upgrade building to GP PracticeView the site start
  2. Completion certificate recordedRecorded in Aug 2020 · 1 unit on this certificateThe month is when the certificate was published, not the date the work finished. The certificate does not say whether it covers all or part of the work. Units on this certificate are not added to other certificates or to the planning total. Last checked 15 Nov 2026.

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 4

Get alerts for Dublin 4Free. We email you when new applications appear.

Free email alerts

Get new Dublin 4 projects by email

New applications, decisions and site starts in Dublin 4, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options