Works to a house · Co. Dublin

53 Lombard Street West, Dublin 8.

Granted 2 Oct 2019 (final grant issued 11 Nov 2019)

We no longer update this application, so we can't email you about it. Get new planning applications in Dublin 8 by email

Key facts

  • Planning application 3761/19 at 53 Lombard Street West, Dublin 8.: Retention of change of roof from double-A to single pitch to match…
  • It was received by Dublin City Council on 15 Aug 2019.
  • Status: Granted 2 Oct 2019 (final grant issued 11 Nov 2019).
  • Work was due to start on 28 Jan 2020, according to the commencement notice. It does not say which contractors or suppliers are appointed.

Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register

More planning applications in Dublin 8 · Planning applications in Co. Dublin

Council register

The council's register shows: Granted on 2 Oct 2019.

Application details as we last saw them in the national register on 2 Jun 2026.

What and where

Retention of change of roof from double-A to single pitch to match…

RETENTION & PERMISSION: Retention permission is sought for: (a) Change of roof from double-A to single pitch to match adjoining house and associated increase in ridge height and removal of brick chimneys; b) Alterations to side elevation of house and boundary wall onto Emorville Avenue including closing of vehicular entrance gates and relocation of pedestrian entrance gate; (c) The height of the flat roof element of the single storey extension to rear which exceeds exempted development allowances; (d) Change to front porch. Planning permission is sought for: (e) Construction of flat roof dormer window to rear roof slope of house; (f) Conversion of attic space to habitable bedroom suite, all to existing single storey end-of-terrace house.

Location
Dublin 8, Co. Dublin Map
Planning reference
3761/19
Application type
Retention permission

Numbers and dates

Project type
Works to a house
Received
15 Aug 2019
Decision to grant
2 Oct 2019
Final grant
11 Nov 2019
Site start notified
28 Jan 2020

Timeline

  1. Application received
  2. Decision to grant
  3. Final grant issued
  4. Site start notified

Outlook

What happens next

Work was due to start on 28 Jan 2020, according to the commencement notice. It does not say which contractors or suppliers are appointed. View the site start

An outlook from the planning record, not a tender or a confirmed start date.

Documents and evidence

Check the record

  • Council planning registerSearch planning.agileapplications.ie for reference 3761/19.Search the register

How we know this

From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.

Site starts

Commencement notices for this permission

  1. 28 Jan 2020Notice filed · New dormer window with habitable attic spaceView the site start

A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.

Explore the area

More planning activity near Dublin 8

Get alerts for Dublin 8Free. We email you when new applications appear.

Free email alerts

Get new Dublin 8 projects by email

New applications, decisions and site starts in Dublin 8, Co. Dublin. Only when there is something new.

We send a confirmation link first. Nothing starts until you click it. You can unsubscribe at any time.

More alert options