- Planning application 3870/23 at 31 St Mary's Road, Ballsbridge, Dublin 4, D04 E9E8: Removal of the roof and internal walls to side infill.
- It was received by Dublin City Council on 31 May 2023.
- Status: Granted 28 Sep 2023 (final grant issued 8 Nov 2023).
- Work was due to start on 2 Jan 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
More planning applications in Dublin 4 · Planning applications in Co. Dublin
Council register
The council's register shows: Granted on 28 Sep 2023.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Removal of the roof and internal walls to side infill
PROTECTED STRUCTURE: Permission for (1) the removal of the roof and internal walls to side infill; (2) the removal of a non-original conservatory (9.2 m²); (3) the demolition of a single-storey lean-to extension to the rear (16 m²); (4) new raised roof and roof lights to side infill extension; (5) new single storey garden room (52 m²), with new courtyard; (6) new opening and double doors between kitchen and living room and new opening and double doors to rear of the return into the garden room, both at ground floor level; (7) modifications to ground floor including raising the floor level in the kitchen and installing a new insulated floor with under floor heating throughout this level, as well as required treatment of damp; (8) minor alterations to internal layouts; (9) new layouts to bathrooms throughout; (10) new bathroom at first floor level; (11) the restoration of original windows throughout, including the installation of new heritage slimline glazing, and to the front door and side gates; (12) repair and replacement as required of rainwater goods; (13) repointing to existing brick and masonry facades and to brick chimneys; (14) minor repairs to roof of main house and the installation of 2 no rooflights; (15) PV panels proposed to the inner slopes of double pile roof and associated works; (16) new window at first floor level; (17) relocation of 2 no windows at attic floor level; (18) upgrading of services; (19) landscaping to front and rear gardens including the installation of a new natural-water lap pool to rear garden; (20) all associated site works. To the mews dwelling; (21) internal alterations at ground and first floors including the relocation of the stairs, new bathroom at ground floor and new layout to bathroom at first floor; (22) construction of a new 23.7 m² single storey side extension; (23) replacement of all non-original windows for timber sash type with acoustic double glazing; (24) installation of new windows and doors and infill of existing, including garage door; (25) removal of roof finishes including asbestos tiles and reinstatement with natural slate to match original; (26) installation of PV panels on south-facing pitch and associated works; (27) replacement of PVC and corroded rainwater goods; (28) repointing to existing stone and brick facades as required and treatment of damp; (29) upgrading of services including installation of UF heating at ground floor level; (30) replacement of existing access gates; (31) installation of electric car port; (32) landscaping and all associated site works.
- Location
- Dublin 4, Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 3870/23
Numbers and dates
- Floor area
- 101 m²
- Project type
- Protected structure
- Received
- 31 May 2023
- Decision to grant
- 28 Sep 2023
- Final grant
- 8 Nov 2023
- Site start notified
- 2 Jan 2024
- Protected structure
- Yes
Timeline
- Application received
- Decision to grant
- Final grant issued
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 3870/23.Search the register
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 2 Jan 2024Notice filed · phase 1 · To the mews dwelling;(21) internal alterations at ground and first floors including the...View the site start
- 2 Jan 2024Notice filed · phase 2 · (1) the removal of the roof and internal walls to side infill; (2) the removal of a...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.