Demolition, Former Scruffy Murphy's Public House, 1/2 Power's Court, Dublin 2... - Planning Application 3932/22Sub08
Dublin / Dublin 2 / Former Scruffy Murphy's Public House, 1/2 Power's Court, Dublin 2, D02 EK50
Source-linked planning record
Demolition, Former Scruffy Murphy's Public House, 1/2 Power's Court, Dublin 2... - Planning Application 3932/22Sub08
Dublin / Dublin 2 / Former Scruffy Murphy's Public House, 1/2 Power's Court, Dublin 2, D02 EK50- PB ref
- PB--2176819663
- Plan ref
- 3932/22Sub08
- Authority
- Dublin City Council
- Stage / date
- New Application / 22 Jun 2026
- Est. value band
- Value not disclosed
- Project class
- Demolition
- Promoter
- Hibernia REIT Plc
- Architect / agent
- AKM Design Group
Source: https://planning.agileapplications.ie/dublincity/application-details/170810
Key facts
Lead summary
- Source
- Dublin City Council public planning register
- Planning authority
- Dublin City Council
- Application reference
- 3932/22Sub08
- Applicant
- Hibernia REIT Plc
- Agent
- AKM Design Group
- Decision stage
- New Application
- Decision due
- 22 Jun 2026
Official description
Verbatim source text
14. The demolition of the existing building and construction of the development shall be managed in accordance with a final Construction and Demolition Waste Management Plan and a final Construction and Environmental Management Plan, both of which shall be submitted to, and agreed in writing with, the planning authority prior to commencement of development. These plans shall provide, inter alia, details and location of proposed construction compounds, details of intended construction practice for the development, including noise management measures, dust and vibration management measures, construction traffic logistics, parking, mobility and access during the construction phase for workers, emergency vehicles and occupants of adjacent residential and commercial premises, and off-site disposal of construction/demolition waste and/or by-products.
Verify against official sourceProject team
Named source parties
- Promoter
- Hibernia REIT Plc
- Planning agent
- AKM Design Group
Lifecycle timeline
Application to site progress
-
Commenced
No commencement indexed Owner-export and BCMS records are indexed only when a reliable source link exists. -
Completed
Completion not recorded Smaller works often do not require a completion certificate.
Likely trades & supplier leads