Infrastructure · Co. Dublin
Demolition of the existing eight storey over basement office building, Co. Dublin
Granted on appeal 1 Nov 2023 (Granted 19 May 2022 by the council)
We no longer update this application, so we can't email you about it. Get new planning applications in Co. Dublin by email
Key facts
- Planning application 4120/21 at Co. Dublin: Demolition of the existing eight storey over basement office building.
- It was received by Dublin City Council on 17 Dec 2021.
- Status: Granted on appeal 1 Nov 2023 (Granted 19 May 2022 by the council).
- Work was due to start on 2 Apr 2024, according to the commencement notice. It does not say which contractors or suppliers are appointed.
Source: the Dublin City Council planning register, as last seen on 2 Jun 2026. Search the council's register
Council register
The council's register shows: Granted on 19 May 2022.
Search the Dublin City planning register
Application details as we last saw them in the national register on 2 Jun 2026.
What and where
Demolition of the existing eight storey over basement office building
The proposed development will consist of the following: • The demolition of the existing eight storey over basement office building on site which has a total gross floor area (GFA) of 3,757.5 sq.m, along with all associated site clearance works; • The construction of a part 4 to part 10 storey office development over basement level, with a café / restaurant unit at ground floor level. The proposal has a GFA of 12,690 sq.m GFA, including basement level; • An office reception area fronting onto the junction of Pembroke Road and Northumberland Road, a café/restaurant unit, office floorspace and ESB substation are proposed at ground floor level; • Ancillary office floorspace, plant rooms, a bin store, attenuation storage, a bike store for 158 no. spaces, 1 no. motorcycle space, e-scooter parking spaces and 9 no. car parking spaces are provided at basement level. 10 no. visitor cycle parking spaces are provided at ground level; • External terraces are provided from first to ninth floor level; • The development provides for pedestrian access from Pembroke Road and Northumberland Road and vehicular and cycle access to the basement car park from Baggot Lane / Northumberland Road; • The development includes screened plant enclosures, green roofs and PV panels at roof level; • The development includes foul and surface water drainage, landscape works, public realm upgrades, boundary treatments, lighting, signage, and all ancillary site development works necessary to facilitate the development. Connection to services / works external to the planning application site boundary will be subject to agreement with the Planning Authority.
- Location
- Co. Dublin Map
- Council
- Dublin City Council
- Planning reference
- 4120/21
Numbers and dates
- Floor area
- 3,758 m²
- Project type
- Infrastructure
- Received
- 17 Dec 2021
- Council decision
- 19 May 2022
- Appeal lodged
- 15 Jun 2022
- Granted on appeal
- 1 Nov 2023
- Site start notified
- 2 Apr 2024
- Protected structure
- Yes
Timeline
- Application received
- Granted by the council
- Appeal lodged
- Appeal decidedGrant permission with revised conditions
- Site start notified
Outlook
What happens next
Work packages named so far
Documents and evidence
Check the record
- Council planning registerSearch planning.agileapplications.ie for reference 4120/21.Search the register
- AppealGrant permission with revised conditions · 313812 / 1 Nov 2023View the appeal record
How we know this
From the Dublin City Council planning register, as last seen on 2 Jun 2026. The council's own file is the official record.
Site starts
Commencement notices for this permission
- 2 Apr 2024Notice filed · This commencement notice without documentation is for the demolition of the existing...View the site start
A commencement notice tells the council that building work is about to start. A completion certificate is filed when it is finished.